Construction Bid questions should be directed to
909/652-6701, or you can visit the construction bid page of the purchasing department site.
Chaffey College serves more than 20,000 students today. Through the Capitol Improvement Project the college will be able to provide education to the residents of the growing Inland Valley, more importantly, those seeking an education at Chaffey.
With the issuance of the first $47.7 million in construction
bonds, Chaffey College began the first phase in the Capitol Improvement
Project – Facilities
Master Plan.
The Facilities Master Plan is
funded by a general obligation bond, Measure L, passed by voters in the Chaffey
Community College District on March 5, 2002.
The bond authorizes the college to issue up to $230 million in
bonds during a 10 year period. A Citizen’s Oversight Committee meets
each quarter to review the financial status and the construction progress.
The Chaffey College Facilities Master Plan consists of new construction,
infrastructure repair, renovation and upgrades to existing facilities, and
procurement of educational equipment.
The Capital Improvement Program has made significant
progress. This is a summary of the completed projects and construction in
progress.
Projects Under Construction
Data and Telecom Cabling-VPA, New Gym, & Physical Science
Architect:
P2S Engineering
Construction Manager:
Bernards
Contractor:
T and D Communications, Inc.
Contract Start:
May 14, 2009
Contract Completion:
November 6, 2009
Original Contract:
$ 154,882
Approved Change Orders:
$ 0
Revised Contract:
$ 154,882
Scope: This project is the installation of data and fiber cabling for the Visual and Performing Arts Complex, New Gymnasium, and the Physical Science Building.
Status: T &D Communications, Inc. completed Phase I on schedule. T & D completed a portion of Phase II (Stadium Press Box), and is expected to complete the New Gymnasium work at the beginning of October 2009. T & D completed Phase III on schedule. Testing and inspection of Phase III is scheduled to complete the first week of October 2009.
Installation of a new splice case for the Stadium Press Box.
Installation of a pull box for New Gymnasium cabling.
Visual and Performing Arts Complex/Music Building
Architect:
Hammel, Green & Abrahamson, Inc.
Construction Manager:
Bernards
Contractor:
ProWest Constructors
Contract Start:
February 2008
Contract Completion:
- Bldg. B & C- Ceramic Lab/Art Studio
Summer 2009
- Bldg. F –Art Complex
Fall 2009
- Bldg. E- Music Building
Summer 2009
Original Contract:
$ 22,145,000
Approved Change Orders:
$ 1,006,475
Revised Contract:
$ 23,151,475
Scope: This project is comprised of four buildings—two new buildings and two buildings that will be renovated. The Performing Arts building, the main building, will be a three-story structure. Including an art complex, digital media labs, photo studio, dance studio, and post-production lab, art studio, audio lab, interior design lab, lecture rooms, and faculty offices, this structure will be 46,000sq. ft. Additionally, there will be a 5,500 sq. ft. one-story music rehearsal building constructed. This will include instrumental and choral rooms. The two existing buildings will be renovated and modernized into a Ceramics lab and Fashion Art studio.
Status: At the Performing Arts Building, ProWest Constructors is completing the plaster at the exterior of the building. The installation of exterior cement panels is on going, and the drywall and texturing of walls is complete at all levels. The upper level mechanical, electrical, and plumbing rough in is complete and finishes are being installed. The installation of roofing material is on going at the Performing Arts Building and carpet installation is complete at all levels. The lecture room seating and bi-fold doors have been installed at the main level. The installation of doors and hardware is on going at all levels. Landscape grading, and the installation of concrete sidewalks around the building, is on going. At the Music Rehearsal Building, ProWest is working on completing the interior punch list items.
Exterior rendering of the main building.
Main level lobby of the Performing Arts Building.
Exterior of the Performing Arts Building – north side.
Exterior of the Performing Arts Building – south side.
Physical Education Athletics-New Gymnasium
Architect:
NTD Architecture
Construction Manager:
Bernards
Contractor:
Edge Development, Inc.
Contract Start:
September 29, 2008
Contract Completion:
December 23, 2009
Original Contract:
$ 8,560,543
Approved Change Orders:
$ 249,057
Revised Contract:
$ 8,809,600
Scope: This project consists of a new 22,000 sq. ft. gymnasium. It will include locker rooms and a snack bar.
Status: At the New Gymnasium, EDGE Development, Inc. has completed installation of all mechanical components and high bay light fixtures. Installation of insulation has begun and will be followed by the installation of drywall. Installation of concrete at the elevator tower has been completed with roofing membrane to follow once the concrete has cured. Painting has begun in the interior of the main gymnasium ceiling, as well as on the exterior site columns and mechanical screen wall framing. Site work is in progress and completion of footings at the south side for seat walls and retaining walls has been accomplished. Additional site work completion includes the north side flatwork and footings for the planter at the entrance. All remaining site work will continue throughout the month of October 2009.
Exterior rendering of the building.
Painting of steel columns at the north end.
Installation of concrete roof at the elevator tower.
Installation of coping cap at the east end roof.
Completion of footings for the planter at the entry.
Projects in Pre-Bid/Planning
Campus Center West
Architect:
MDA Johnson Favaro
Construction Manager:
Bernards
Contractor:
To Be Announced
Contract Start:
To Be Announced
Contract Completion:
To Be Announced
Original Contract:
To Be Announced
Approved Change Orders:
To Be Announced
Revised Contract:
To Be Announced
Scope: The existing Campus Center West building will be demolished, and construction of a new 16,454 sq. ft. Campus Center West will be constructed in its place. Select modernization of the Campus Center East will occur as well.
Status: The project has been approved to proceed to the bid stage by the Division of the State Architect. The bid documents, final verification of the project, and swing space plans are in process with the College and MDA Johnson Favaro.
Rendering of interior cooridor.
Floor plan of new building.
Rendering of interior dining area.
Fontana Phase III-Academic Building
Architect:
MDA Johnson Favaro
Construction Manager:
Bernards
Contractor:
To Be Announced
Contract Start:
To Be Announced
Contract Completion:
To Be Announced
Original Contract:
To Be Announced
Approved Change Orders:
To Be Announced
Revised Contract:
To Be Announced
Scope: Comprised of 30,400 sq ft., this will be a new academic building. Inside the building, there will be four classrooms, two labs with prep rooms, a library, a bookstore, student lounge, dance studio, and administration offices.
Status: The Division of the State Architect has provided final approval of the project. The project has been submitted to the State Chancellor’s office for approval to proceed to bid and award of the contract. Tentative construction is to start in fall 2009, subject to approval of state funding.
Exterior rendering of the building looking north.
First floor plan layout.
Second floor plan layout.
Omnitrans Transit Center
Architect:
HMC Architects
Construction Manager:
Bernards
Contractor:
To Be Determined
Contract Start:
To Be Determined
Contract Completion:
To Be Determined
Original Contract:
To Be Announced
Approved Change Orders:
To Be Announced
Revised Contract:
To Be Announced
Scope: Design and construction of a new transit bus center for the loading and unloading of the Omnitrans buses on the Rancho Cucamonga campus.
Status: The project is in the pre-design development / pre-construction phase. HMC Architects is working with Omnitrans and the College on the design issues of the Transit Center. Based upon the approval process with DSA and Omnitrans, tentative construction is scheduled for summer 2010.
Physical Education Facility - Gymnasium Remodel
Architect:
NTD Architecture
Construction Manager:
Bernards
Contractor:
To Be Announced
Contract Start:
To Be Announced
Contract Completion:
To Be Announced
Original Contract:
To Be Announced
Approved Change Orders:
To Be Announced
Revised Contract:
To Be Announced
Scope: Renovation of the 30,843 sq. ft. existing athletics building.
Status: The bid documents are being finalized, and the bid period will run from early October 2009 through mid November 2009. Approval of the General Contractor’s contract is scheduled for the December 2009 board meeting. Construction is scheduled to begin early February 2010.
View looking south of the existing Gymnasium.
Measure “L” Build Out Future Projects
Central Plant Build-Out
Status: This project is scheduled as an energy project and is in the design development phase with P2S Engineering, Inc.
Physical Science-Northwest Section and
Southeast Section Remodel
Status: This project is in the design development/programming phase with WWCOT Architects.
Liberal Arts and Letters
Status: Awaiting approval of the State funding proposal pending passage of the State Revenue Bond measure.
Library Remodel / Expansion
Status: Awaiting approval of the State funding proposal pending passage of the State Revenue Bond measure.
Projects Completed
Fontana Phase III-Parking Lot
Architect:
HMC Architects
Construction Manager:
Bernards
Contractor:
Bogh Engineering, Inc.
Contract Start:
May 11, 2009
Contract Completion:
October 5, 2009
Original Contract:
$ 1,089,000
Approved Change Orders:
$ 42,618
Revised Contract:
$ 1,131,618
Scope: The Fontana Phase III Parking Lot project consists of the construction of a new parking lot, landscaping, driveway/fire lanes, walkways, utilities, lighting, and signage at the Fontana Campus.
Complete parking lot paved and striped.
Bio-swale and walkway pavers installed
Chino Health Science Parking Lot
Architect:
MDA Johnson Favaro
Construction Manager:
Chaffey College
Contractor:
Laird Construction Co., Inc.
Contract Start:
June 15, 2009
Contract Completion:
August 15, 2009
Original Contract:
$ 414,550
Approved Change Orders:
$ 0
Revised Contract:
$ 414,550
Scope: The construction of a 100,000 sq. ft. parking lot with 194 parking stalls south and west of the existing parking lots.The parking lot is adjacent to the existing Main Instructional Building located on the Chino Campus.
Chino Campus parking lot, view looking west.
Language Arts/Social Science-HVAC Project
Architect:
P2S Engineering
Construction Manager:
Bernards
Contractor:
Siemens
Contract Start:
May 15, 2009
Contract Completion:
August 14, 2009
Original Contract:
$ 2,700,000
Approved Change Orders:
$ 95,164
Revised Contract:
$ 2,795,164
Scope: This is an energy project upgrade to the Language Arts and Social Science building, which will include installation of new air handling equipment and new lighting systems.
Social Science-Completed view of the classroom.
Physical Science Complex-Roof Replacement
Architect:
WWCOT Architect
Construction Manager:
Chaffey College
Contractor:
Cabral Roofing and Waterproofing Corp.
Contract Start:
May 21, 2009
Contract Completion:
July 17, 2009
Original Contract:
$ 623,636
Approved Change Orders:
$ 0
Revised Contract:
$ 623,636
Scope: Replacement of the existing roof at the Physical Science building with a standing seam metal roof.
Completed roof at the Physical Science building.
Library Lawn/Fontana Phase II Landscaping
Architect:
Steve Frenken Landscape Architecture
Construction Manager:
Bernards
Contractor:
Land Forms Landscape Construction
Contract Start:
August 20, 2008
Contract Completion:
November 25, 2008
Original Contract:
$385,000
Approved Change Orders:
($450)
Revised Contract:
$384,550
Scope: This project consists of landscaping and creating the irrigation system for the Fontana Campus Phase II project and the library lawn area at the Rancho Cucamonga campus.
Landscaping at the Fontana Campus.
Landscaping at the Rancho Cucamonga Campus.
Health and Life Science (HLS) Re-Roofing
Architect:
WWCOT Architects
Construction Manager:
Bernards
Contractor:
Best Contracting Services, Inc.
Contract Start:
January 1, 2008
Contract Completion:
June 13, 2008
Original Contract:
$456,169
Approved Change Orders:
$16, 383
Revised Contract:
$472,552
Scope: Comprised of the Health Science Building and the two Life Science buildings, the Health and Life Science Re-Roofing Project, consists of the removal of an existing built up roof on all three locations, and the construction of a new standing seam metal roof.
Newly installed metal roof.
Physical, Health, Life Science (PHLS) Renovations
Architect:
WWCOT Architects
Construction Manager:
Bernards
Contractor:
PW Construction, Inc.
Contract Start:
June 16, 2007
Contract Completion:
Phase 1: June 18, 2008
Phase 2: August 15, 2008
Original Contract:
$8,196,500
Approved Change Orders:
$871,357
Revised Contract:
$9,067,857
Scope: Comprised of 22,997 sq. ft., the Physical, Health, and Life Science Project consists of the renovation of five existing buildings.
Completed dental lab at Physical Science.
New Marquee Sign
Architect:
Hammel, Green & Abrahamson, Inc.
Construction Manager:
Bernards
Contractor:
Quiel Bros. Electric Sign
Contract Start:
December 27, 2007
Contract Completion:
June 2008
Original Contract:
$180,000
Approved Change Orders:
$1,500
Revised Contract:
$181,500
Scope: Removal and replacement of the existing marquee sign located at the Haven Avenue entrance. The new marquee sign is a double-sided display board constructed of brushed aluminum and baked enamel surfaces.
New marquee sign at Haven Avenue entrance.
Parking Lot #12/Elevator
Architect:
GKK Works
Construction Manager:
Bernards
Contractor:
Edge Development, Inc.
Contract Start:
May 16, 2007
Contract Completion:
November 11, 2007
Original Contract:
1,897,007
Approved Change Orders:
$68,534
Revised Contract:
$1,965,541
Scope: This project completely re-constructs Parking Lot 12 (Phase 1) including two accessible parking areas, sidewalks, lights and landscaping. An elevator (Phase 2) was also constructed connecting the VSS facility to Parking Lot 12.