Construction Bid questions should be directed to
909/652-6701, or you can visit the construction bid page of the purchasing department site.
Chaffey College serves more than 20,000 students today. Through the Capitol Improvement Project the college will be able to provide education to the residents of the growing Inland Valley, more importantly, those seeking an education at Chaffey.
With the issuance of the first $47.7 million in construction
bonds, Chaffey College began the first phase in the Capitol Improvement
Project – Facilities
Master Plan.
The Facilities Master Plan is
funded by a general obligation bond, Measure L, passed by voters in the Chaffey
Community College District on March 5, 2002.
The bond authorizes the college to issue up to $230 million in
bonds during a 10 year period. A Citizen’s Oversight Committee meets
each quarter to review the financial status and the construction progress.
The Chaffey College Facilities Master Plan consists of new construction,
infrastructure repair, renovation and upgrades to existing facilities, and
procurement of educational equipment.
The Capital Improvement Program has made significant
progress. This is a summary of the completed projects and construction in
progress.
Projects Under Construction Nothing to report at this time.
Scope: Renovation of the 30,843 sq. ft. existing athletics building.
Status: USS Cal Builders, Inc. has been awarded the
contract for the Physical Ed Facility Gym Renovation,
and is currently in the process of preparing their
schedule and fencing plans for review. Swing space
moving of remaining surplus furniture is in process
for anticipation of the construction start date of
February 1, 2010. Completion of the project, is
expected by November 2010.
View looking south of the existing Gymnasium.
VPA North – Fire Lane
Architect:
Associated Engineers
Construction Manager:
Bernards
Contractor:
To Be Announced
Contract Start:
To Be Announced
Contract Completion:
To Be Announced
Contract Amount:
To Be Announced
Approved Change Orders:
To Be Announced
Revised Contract Amount:
To Be Announced
Scope: The project includes the renovation of the
existing fire lane northeast of the EEC Building and
south of the Language Arts Building. The project will
rework existing contours of the fire lane, while
connecting it to the new Visual and Performing Arts
Complex fire lane in compliance with the Americans
with Disabilities Act requirements.
Status: The bid opening occurred January 26, 2010.
Bernards and the College are currently going through
the bid verification process. Approval of the General
Contractor’s contract is scheduled for the February
2010 Board meeting. Construction is scheduled to
begin mid March 2010.
View looking west of the VPA North Fire Lane.
Fontana Phase III-Academic Building
Architect:
HMC Architects
Construction Manager:
Bernards
Contractor:
To Be Announced
Contract Start:
To Be Announced
Contract Completion:
To Be Announced
Original Contract:
To Be Announced
Approved Change Orders:
To Be Announced
Revised Contract:
To Be Announced
Scope: Comprised of 30,400 sq ft., this will be a new academic building. Inside the building, there will be four classrooms, two labs with prep rooms, a library, a bookstore, student lounge, dance studio, and administration offices.
Status: Bid documents are being prepared to begin
the bid and award process by mid January 2010.
Construction is tentatively scheduled to begin by mid
March 2010, with completion by mid summer 2011.
Exterior rendering of the building looking north.
First floor plan layout.
Second floor plan layout.
VPA Landscape Addition
Architect:
Soltis Landscape Services
Construction Manager:
Bernards
Contractor:
To Be Announced
Contract Start:
To Be Announced
Contract Completion:
To Be Announced
Contract Amount:
To Be Announced
Approved Change Orders:
To Be Announced
Revised Contract Amount:
To Be Announced
Scope: The project includes the landscaping and
irrigation of the areas adjacent to the Visual and
Performing Arts Complex.
Status: The bid process has begun as of January 26, 2010. The job walk is scheduled for February 9,
2010, with the bid opening occurring March 2, 2010. Construction is anticipated to begin mid April
2010, with completion by July 2010.
View looking east of the area to be landscaped
south of the Performing Arts Building.
View looking west of the area to be landscaped
southwest of the Performing Arts Building.
Projects in Pre-Bid/Planning
Campus Center West
Architect:
MDA Johnson Favaro
Construction Manager:
Bernards
Contractor:
To Be Announced
Contract Start:
To Be Announced
Contract Completion:
To Be Announced
Contract Amount:
To Be Announced
Approved Change Orders:
To Be Announced
Revised Contract Amount:
To Be Announced
Scope: The existing Campus Center West building will be demolished, and construction of a new 16,454 sq. ft. Campus Center West will be constructed in its place. Select modernization of the Campus Center East will occur as well.
Status: The Division of the State Architect has
approved the project. The bid documents, final
verification of the project/scope of work, and swing
space plans are in process with the College, MDA
Johnson Favaro, and Bernards. Construction is
tentatively scheduled to begin late May 2010.
Campus Center West rendering of exterior and
landscaping.
Floor plan of new building.
Rendering of interior dining area.
Omnitrans Transit Center
Architect:
HMC Architects
Construction Manager:
Bernards
Contractor:
To Be Determined
Contract Start:
To Be Determined
Contract Completion:
To Be Determined
Original Contract:
To Be Announced
Approved Change Orders:
To Be Announced
Revised Contract:
To Be Announced
Scope: Design and construction of a new transit bus center for the loading and unloading of the Omnitrans buses on the Rancho Cucamonga campus.
Status: The project is in the pre-design development / pre-construction phase. HMC Architects is
working with Omnitrans and the College on the design issues of the Transit Center. Based upon the
approval process with DSA and Omnitrans, tentative construction is scheduled for summer 2010.
Measure “L” Build Out Future Projects
Physical Science-Northwest Section and Southeast
Section Remodel
Status: This project is in the programming phase/design development. Architect: WWCOT Architects
Math Success Center Renovation
Status: This project is in design development. Architect: WWCOT Architects
Business Education Renovation
Status: This project is in design development. Architect: WWCOT Architects
Aviary Landscape
Status: This project is in design development. Architect: Soltis Landscape Services
SSA-East Door Entrances
Status: This project is awaiting DSA approval. Architect: HMC Architects
PE Athletics-Parking Lot and Flagpole
Status: This project is in design development. Engineer: Associated Engineers
Fire Alarm-Campus Center East, IT, & Planetarium
Status: This project is in design development. Engineer: P2S Engineering, Inc.
Central Plant Build-Out
Status: This project is scheduled as an energy project and is in design development. Engineer: P2S Engineering, Inc.
Liberal Arts and Letters
Status: Awaiting approval of the State funding proposal pending passage of the State Revenue Bond
measure.
Library Remodel / Expansion
Status: Awaiting approval of the State funding proposal pending passage of the State Revenue Bond
measure.
Projects Completed
Physical Education Facility-New Gymnasium
Architect:
NTD Architecture
Construction Manager:
Bernards
Contractor:
Edge Development, Inc.
Contract Start:
September 29, 2008
Contract Completion:
December 23, 2009
Original Contract:
$ 8,560,543
Approved Change Orders:
$ 341,657
Revised Contract:
$ 8,902,200
Scope: This project consists of a new 22,000 sq. ft. gymnasium. It will include locker rooms and a snack bar.
Interior view of completed installation of wood
flooring, bleachers, and scoreboard.
Visual and Performing Arts Complex/Music Building
Architect:
Hammel, Green & Abrahamson, Inc.
Construction Manager:
Bernards
Contractor:
ProWest Constructors
Contract Start:
February 2008
Contract Completion:
- Bldg. B & C- Ceramic Lab/Art Studio
Summer 2009
- Bldg. F –Art Complex
Fall 2009
- Bldg. E- Music Building
Summer 2009
Original Contract:
$ 22,145,000
Approved Change Orders:
$ 1,175,619
Revised Contract:
$ 23,320,619
Scope: This project is comprised of four buildings—two new buildings and two buildings that will be renovated. The Performing Arts building, the main building, will be a three-story structure. Including an art complex, digital media labs, photo studio, dance studio, and post-production lab, art studio, audio lab, interior design lab, lecture rooms, and faculty offices, this structure will be 46,000sq. ft. Additionally, there will be a 5,500 sq. ft. one-story music rehearsal building constructed. This will include instrumental and choral rooms. The two existing buildings will be renovated and modernized into a Ceramics lab and Fashion Art studio.
Exterior of the Performing Arts Building-south
side.
Data and Telecom Cabling-VPA, New Gym, & Physical Science
Architect:
P2S Engineering
Construction Manager:
Bernards
Contractor:
T & D Communications, Inc.
Contract Start:
May 14, 2009
Contract Completion:
November 6, 2009
Original Contract:
$ 154,882
Approved Change Orders:
$ ($5,127)
Revised Contract:
$ 149,755
Scope: The Data and Telecom Cabling project involves the
installation of new data and fiber cabling for the Visual and
Performing Arts Complex, New Gymnasium, and the
Physical Science Building. The work was seperated into
three (3) phases: Phase I-New cabling to the Fashion,
Ceramics, and Music buildings in the Performing Arts
Complex and the Physical Science Building; Phase II-New
cabling to the Stadium Press Box and New Gymnasium;
and Phase III-New cabling to the Performing Arts Building
in the Performing Arts Complex.
Completed installation of fiber optic cable in
the Suitomo panel.
Fontana Phase III-Parking Lot
Architect:
HMC Architects
Construction Manager:
Bernards
Contractor:
Bogh Engineering, Inc.
Contract Start:
May 11, 2009
Contract Completion:
October 5, 2009
Original Contract:
$ 1,089,000
Approved Change Orders:
$ 42,618
Revised Contract:
$ 1,131,618
Scope: The Fontana Phase III Parking Lot project consists of the construction of a new parking lot, landscaping, driveway/fire lanes, walkways, utilities, lighting, and signage at the Fontana Campus.
Bio-swale and walkway pavers installed
Chino Health Science Parking Lot
Architect:
MDA Johnson Favaro
Construction Manager:
Chaffey College
Contractor:
Laird Construction Co., Inc.
Contract Start:
June 15, 2009
Contract Completion:
August 15, 2009
Original Contract:
$ 414,550
Approved Change Orders:
$ 0
Revised Contract:
$ 414,550
Scope: The construction of a 100,000 sq. ft. parking lot with 194 parking stalls south and west of the existing parking lots.The parking lot is adjacent to the existing Main Instructional Building located on the Chino Campus.
Chino Campus parking lot, view looking west.
Language Arts/Social Science-HVAC Project
Architect:
P2S Engineering
Construction Manager:
Bernards
Contractor:
Siemens
Contract Start:
May 15, 2009
Contract Completion:
August 14, 2009
Original Contract:
$ 2,700,000
Approved Change Orders:
$ 103,828
Revised Contract:
$ 2,803,828
Scope: Energy project upgrade to the Language Arts and
Social Science buildings, which includes installation of new
air handling equipment and new lighting systems.
Social Science-Completed view of the classroom.
Physical Science Complex-Roof Replacement
Architect:
WWCOT Architect
Construction Manager:
Chaffey College
Contractor:
Cabral Roofing and Waterproofing Corp.
Contract Start:
May 21, 2009
Contract Completion:
July 17, 2009
Original Contract:
$ 623,636
Approved Change Orders:
$ 0
Revised Contract:
$ 623,636
Scope: Replacement of the existing roof at the Physical Science building with a standing seam metal roof.
Completed roof at the Physical Science building.
Library Lawn/Fontana Phase II Landscaping
Architect:
Steve Frenken Landscape Architecture
Construction Manager:
Bernards
Contractor:
Land Forms Landscape Construction
Contract Start:
August 20, 2008
Contract Completion:
November 25, 2008
Original Contract:
$385,000
Approved Change Orders:
($450)
Revised Contract:
$384,550
Scope: This project consists of landscaping and creating the irrigation system for the Fontana Campus Phase II project and the library lawn area at the Rancho Cucamonga campus.
Landscaping at the Fontana Campus.
Landscaping at the Rancho Cucamonga Campus.
Health and Life Science (HLS) Re-Roofing
Architect:
WWCOT Architects
Construction Manager:
Bernards
Contractor:
Best Contracting Services, Inc.
Contract Start:
January 1, 2008
Contract Completion:
June 13, 2008
Original Contract:
$456,169
Approved Change Orders:
$16, 383
Revised Contract:
$472,552
Scope: Comprised of the Health Science Building and the two Life Science buildings, the Health and Life Science Re-Roofing Project, consists of the removal of an existing built up roof on all three locations, and the construction of a new standing seam metal roof.
Newly installed metal roof.
Physical, Health, Life Science (PHLS) Renovations
Architect:
WWCOT Architects
Construction Manager:
Bernards
Contractor:
PW Construction, Inc.
Contract Start:
June 16, 2007
Contract Completion:
Phase 1: June 18, 2008
Phase 2: August 15, 2008
Original Contract:
$8,196,500
Approved Change Orders:
$871,357
Revised Contract:
$9,067,857
Scope: Comprised of 22,997 sq. ft., the Physical, Health, and Life Science Project consists of the renovation of five existing buildings.
Completed dental lab at the Physical Science
Building.
New Marquee Sign
Architect:
Hammel, Green & Abrahamson, Inc.
Construction Manager:
Bernards
Contractor:
Quiel Bros. Electric Sign
Contract Start:
December 27, 2007
Contract Completion:
June 2008
Original Contract:
$180,000
Approved Change Orders:
$1,500
Revised Contract:
$181,500
Scope: Removal and replacement of the existing marquee sign located at the Haven Avenue entrance. The new marquee sign is a double-sided display board constructed of brushed aluminum and baked enamel surfaces.
New marquee sign at Haven Avenue.
Parking Lot #12/Elevator
Architect:
GKK Works
Construction Manager:
Bernards
Contractor:
Edge Development, Inc.
Contract Start:
May 16, 2007
Contract Completion:
November 11, 2007
Original Contract:
1,897,007
Approved Change Orders:
$68,534
Revised Contract:
$1,965,541
Scope: This project completely re-constructs Parking Lot 12 (Phase 1) including two accessible parking areas, sidewalks, lights and landscaping. An elevator (Phase 2) was also constructed connecting the VSS facility to Parking Lot 12.