Chaffey Logo link

 
 




Construction Update

Chaffey College Measure L Citizens’ Oversight Committee

Latest News and Announcements


Download Reports

    2014
    February
    April
    May
    June

    2013
    January
    February
    March
    April
    July
    August
    September
    October
    November
    December

    2012
    January
    February
    March
    April
    May
    June
    July
    August
    September
    October
    November
    December

    2011
    January
    February
    March
    April
    May
    June
    July
    August
    September
    October
    November
    December

    2010
    January
    February
    March
    April
    May
    June
    July
    August
    September
    October
    November
    December

    2009
    January
    February
    March
    April
    May
    June
    July
    August
    September
    October
    November
    December

    2008
    December


Construction Bid questions should be directed to 909/652-6701, or you can visit the construction bid page of the purchasing department site.


  bernards


construction update banner

Chaffey College serves more than 20,000 students today. Through the Capitol Improvement Project the college will be able to provide education to the residents of the growing Inland Valley, more importantly, those seeking an education at Chaffey.
Recent Completions | Under Construction | In Pre-Bid and Award | In Pre-Bid/Planning | Future Projects | Program Budget |

Overview


With the issuance of the first $47.7 million in construction bonds, Chaffey College began the first phase in the Capitol Improvement Project – Facilities Master Plan. The Facilities Master Plan is funded by a general obligation bond, Measure L, passed by voters in the Chaffey Community College District on March 5, 2002. The bond authorizes the college to issue up to $230 million in bonds during a 10 year period. A Citizen’s Oversight Committee meets each quarter to review the financial status and the construction progress. The Chaffey College Facilities Master Plan consists of new construction, infrastructure repair, renovation and upgrades to existing facilities, and procurement of educational equipment. The Capital Improvement Program has made significant progress. This is a summary of the completed projects and construction in progress.


Projects Under Construction




Projects in Bid and Award




Projects in Pre-Bid/Planning

Measure “L” Build Out Future Projects


   Central Plant Build-Out – Phase 1C – TES Tank

Status: The project includes the construction of a new thermal energy storage tank and the addition of six boilers at the Central Plant. Both have been approved by the Division of the State Architect (DSA). Construction is tentatively scheduled to begin in the summer 2014.
Architect: P2S Engineering, Inc.

   Language / Liberal Arts and Letters

Status:The project is awaiting approval of the initial project proposal (IPP) with the State Chancellor’s Office.

   Library Remodel / Expansion

Status: The project is awaiting approval of the initial project proposal (IPP) with the State Chancellor’s Office.


   Library Security Cameras

Status: The project is the installation of a video surveillance system with both interior and exterior cameras for full coverage. Installation is scheduled for summer 2014..

   Business Education Re-Roof

Status: The project is in the project development stage with the Campus Facilities Department.




Projects Completed


   Athletic Field Parking Lot and Flagpole

Engineer: Associated Engineers
Construction Manager: Chaffey College
Contractor: Laird Construction Company, Inc.
Contract Start: October 5, 2012
Contract Completion: January 15, 2013
Original Contract: $697,000
Approved Change Orders: $26,966
Revised Contract: $723,966

Scope:The project includes the construction of a new 116,000 square foot, 260-space decomposed granite parking lot to serve the needs of adjacent athletic fields.

ath lot
Completed installation of decomposed granite, Code Blue phones, and light poles facing southeast.




   North Parking Lot - Catch Basin Addition

Engineer: Fuscoe Engineering, Inc.
Construction Manager: Bernards
Contractor: Excel Paving Company
Contract Start: July 2, 2012
Contract Completion: August 3, 2012
Original Contract: $127,965
Approved Change Orders: $0
Revised Contract: $127,965

Scope: The project includes the addition of drainage systems at Parking Lot 4 to address storm drain overflow.

basin
View of completed catch basin installation at Parking Lot 4 facing east.




   Health Science Pathway

Engineer: Fuscoe Engineering, Inc.
Construction Manager: Bernards
Contractor: Laird Construction/KAR Construction
Ryko Construction/Raffi's Metal Design
Contract Start: March 19, 2012
Contract Completion: May 31, 2012
Original Contract: $121,832
Approved Change Orders: $6,123
Revised Contract: $127,955

Scope: Addition of a concrete pathway from Health Sciences to the Michael Alexander Campus Center.


pathway
View of completed pathway facing northeast.




   Greenhouse

Engineer: P2S Engineering, Inc.
Construction Manager: Chaffey College
Contractor: Cavalier Construction/VO Builders
Contract Start: September 14, 2011
Contract Completion: April 30, 2012
Original Contract: $148,000
Approved Change Orders: ($216)
Revised Contract: $147,784

Scope: Installation of a prefabricated greenhouse structure at the Science Complex.


greenhouse
View of completed structure and concrete walkway.



   Omnitrans – Media Plan

Construction Manager: Bernards
Contractor: Daniel's Electric Construction, Inc.
Black Box Network Services/Siemens
Contract Start: November 1, 2011
Contract Completion: January 31, 2012
Original Contract: $71,354
Approved Change Orders: $0
Revised Contract: $71,354

Scope: Addition of security cameras and electrical upgrades in the Omnitrans parking lot.

omnitrans
New security camera installed on light pole at the Omnitrans parking lot.




  Michael Alexander Campus Center

Architect: MDA Johnson Favaro
Construction Manager: Bernards
Contractor: See Multi-Prime Contracts
Contract Start: June 21, 2010
Contract Completion: August 11, 2011
Original Contract: $6,686,215
Approved Change Orders: $216,370
Revised Contract: $6,902,585
Multi-Prime Contracts (19): See Below
BP 01 – General Construction: USS Cal Builders, Inc. $ 643,536
BP 02 – Earthwork, Grading & Paving: Crew, Inc. 774,048
BP 03 – Concrete: ASR Constructors, Inc. 567,496
BP 04 – Masonry: ASR Constructors, Inc. 178,000
BP 05 – Structural Steel: KCB Towers, Inc. 574,290
BP 06 – Casework: K & Z Cabinet Co., Inc. 134,531
BP 07 – Roofing & Sheet Metal: Chapman Coast Roof Co., Inc. 220,449
BP 08 – Aluminum Storefront & Glazing: E & R Glass Contractors, Inc. 167,868
BP 09 – Framing, Drywall, Fireproofing, Lath & Plaster: Caston Plastering & Drywall, Inc. 698,372
BP 10 – Ceramic Tile: Continental Marble and Tile Company 74,104
BP 11 – Acoustical Ceilings: Commercial Interiors Acoustics, Inc. 47,315
BP 12 – Flooring: Donald M. Hoover Company 95,998
BP 13 – Painting: Triumph Painting 65,626
BP 14 – Plumbing: Nile ASR/Duke Constructors 467,902
BP 15 – HVAC: West-Tech Mechanical, Inc. 674,289
BP 16 – Electrical: Daniel's Electric Construction Co., Inc. 927,339
BP 17 – Landscape & Irrigation: Martinez Landscaping Co., Inc. 147,939
BP 18 – Fire Protection: JPI Development, Inc. 92,695
BP 19 – Kitchen Equipment: R.W. Smith & Co., Inc. 350,688

macc
Aerial view of the completed building facing northeast.

Scope: Demolition of the existing Campus Center West Building and the construction of a new 16,400 sq. ft. two story Campus Center Building, including a student cafeteria, faculty dining room, health services, career services resource center, extended opportunity programs and services, and student government offices. Renovation of approximately 1,700 sq. ft. of the existing Campus Center East Building.

macc
Completed student dining area at first floor.



   Omnitrans – Roadway Work

Construction Manager: Bernards
Contractor: Mission Paving and Sealing, Inc.
Contract Start: December 19, 2011
Contract Completion: January 16, 2012
Original Contract: $89,985
Approved Change Orders: $0
Revised Contract: $89,985

Scope: Additional road and parking lot work at College Drive.


omnitrans
Completion of asphalt placement and striping at College Drive.



   Business Education Renovation

Architect: DLR Group WWCOT
Construction Manager: Bernards
Contractor: Southland Industries, Inc.
Contract Start: May 31, 2011
Contract Completion: August 7, 2011
Original Contract: $3,155,168
Approved Change Orders: $212,371
Revised Contract: $3,367,539

Scope: Energy upgrades, along with interior and exterior renovations, of the Business Education building.

business education
Completed installation of furniture and equipment at renovated classroom.



  Fontana Phase III-Academic Building

Architect: HMC Architects
Construction Manager: Bernards
Contractor: See Multi-Prime Contracts
Contract Start: March 16, 2010
Contract Completion: June 24, 2011
Original Contract: $ 7,305,036
Approved Change Orders: $ 533,970
Revised Contract: $ 7,839,006
Multi-Prime Contracts (17): See Below
FABP 01 – General Construction: ISEC, Inc. $ 621,073
FABP 02 – Earthwork, Grading & Paving: Crew, Inc. 200,216
FABP 03 – Concrete: Rossi Concrete, Inc. 561,334
FABP 04 – Fire Protection: Kincaid Industries, Inc. 167,131
FABP 05 – Structural, Misc. Steel & Metal Decking: Columbia Steel, Inc. 665,962
FABP 06 – Casework & Millwork: ISEC, Inc. 257,679
FABP 07 – Roofing & Sheet Metal: Waterproofing Experts, Inc. 523,021
FABP 08 – Aluminum Storefront & Glazing: Best Contracting Services, Inc. 567,739
FABP 09 – Framing, Drywall, Fireproofing, Lath & Plaster: Caston Plastering & Drywall, Inc. 980,072
FABP 10 – Ceramic Tile: J. Colavin & Son, Inc. 55,184
FABP 11 – Acoustical Ceilings: KHS&S Contractors, Inc. 100,764
FABP 12 – Flooring: Donald M. Hoover Company 167,415
FABP 13 – Painting: AJ Fistes Corporation 92,507
FABP 14 – Plumbing: Nile Advanced Construction, Inc. 398,600
FABP 15 – HVAC: West-Tech Mechanical, Inc. 940,651
FABP 16 – Electrical: R.I.S. Electrical Contractors, Inc. 1,389,997
FABP 17 – Landscape & Irrigation: ASR Constructors, Inc. 149,660

Scope: Comprised of 30,400 sq ft., this will be a new academic building. Inside the building, there will be four classrooms, two labs with prep rooms, a library, a bookstore, student lounge, dance studio, and administration offices.

fontana
Building exterior facing southeast.

fontana
Completed casework and fixture installation at laboratory.



   Fire Alarm Upgrades

Architect: P2S Engineering, Inc.
Construction Manager: Chaffey College
Contractor: Siemens Industry, Inc.
Contract Start: April 18, 2011
Contract Completion: November 3, 2011
Original Contract: $193,141
Approved Change Orders: $0
Revised Contract: $193,141

Scope: Upgrade and redesign of existing fire alarm systems at the Campus Center East, Information Services, and Planetarium buildings.


fire alarm
Installation of upgraded fire alarm at Information Services.




   Student Services and Administration
   East Entrance Doors

Architect: HMC Architects
Construction Manager: Chaffey College
Contractor: Daniel's Electric/E & R Glass
Contract Start: September 8, 2011
Contract Completion: October 31, 2011
Original Contract: $73,000
Approved Change Orders: $1,805
Revised Contract: $74,805

Scope: Installation of an automatic sliding door and upgrades to existing doors at the Student Services/Administration building.


door
Completed door installation at east entrance to the Student Services and Administration building.




  Physical Education Facility - Gymnasium Renovation

Architect: NTD Architecture
Construction Manager: Bernards
Contractor: USS Cal Builders, Inc.
Contract Start: February 1, 2010
Contract Completion: February 4, 2011
Original Contract: $ 4,694,000
Approved Change Orders: $ 465,508
Revised Contract: $ 5,159,508

Scope: Renovation of the 30,843 sq. ft. existing athletics building.


gym
New resilient wood flooring and striping at the main gymnasium floor.
     
gym
Completed ceramic tile, mirrors, plumbing fixtures, and partitions at the men's restroom.
 



  Central Plant Build Out-Hot Water Upgrade

Architect: P2S Engineering, Inc.
Construction Manager: Bernards
Contractor: Hickman Mechanical, Inc.
Contract Start: October 27, 2010
Contract Completion: February 11, 2011
Contract Amount: $ 148,800
Approved Change Orders: $ 12,234
Revised Contract Amount: $ 161,034

Scope: The project consists of upgrades to the existing boiler system and expansion tanks at the Central Plant-Phase One.

central plant
Interior view of retrofitted boilers.



  Aviary Landscape

Architect: Soltis Landscape Services, Inc.
Construction Manager: Chaffey College
Contractor: Nature Tech Landscape
Contract Start: September 15, 2010
Contract Completion: February 22, 2011
Contract Amount: $ 105,000
Approved Change Orders: $ 10,210
Revised Contract Amount: $ 115,210

Scope: The installation of landscape within the Aviary structure.

aviary
Completed habitat installation and landscaping looking south.



  Omnitrans Transit Center

Architect: HMC Architects
Construction Manager: Bernards
Contractor: Young Contractors, Inc.
Contract Start: June 4, 2010
Contract Completion: November 24, 2010
Original Contract: $1,681,000
Approved Change Orders: $84,738
Revised Contract: $1,765,738

Scope: Design and construction of a new transit bus center for the loading and unloading of the Omnitrans buses on the Rancho Cucamonga campus.

omnitrans
Completed bus shelter looking west.



  VPA Landscape Addition

Architect: Soltis Landscape Services
Construction Manager: Bernards
Contractor: Elite Landscaping, Inc.
Contract Start: April 19, 2010
Contract Completion: December 12, 2010
Contract Amount: $ 247,770
Approved Change Orders: $ 10,337
Revised Contract Amount: $ 258,107

Scope: The project includes the landscaping and irrigation of the areas adjacent to the Visual and Performing Arts Complex.


landscape
New rock swale and shrubs at tree alley, south of the Center for the Arts building.



  Physical Science Renovation

Architect: DLR Group WWCOT
Construction Manager: Bernards
Contractor: Southland Industries
Contract Start: June 1, 2010
Contract Completion: July 31, 2010
Original Contract: $ 2,094,591
Approved Change Orders: $ 160,201
Revised Contract: $ 2,254,792

Scope: This is an energy project services contract, which includes energy efficient lighting amd HVAC systems and controls, along with interior renovations.

physical science
Interior view of completed classroom, and lighting upgrades.




  Math Success Center

Architect: DLR Group WWCOT
Construction Manager: Bernards
Contractor: Southland Industries
Contract Start: June 1, 2010
Contract Completion: July 31, 2010
Original Contract: $ 893,698
Approved Change Orders: $ 14,908
Revised Contract: $ 908,606

Scope: This is an energy project services contract, which includes energy efficient lighting amd HVAC systems and controls, along with interior renovations.

math sc
Interior view of completed lighting upgrades and classroom.



  Panther Express Convenience Store

Architect: HMC Architects
Construction Manager: Bernards
Contractor: KAR Construction/Mobile Modular
Contract Start: July 26, 2010
Contract Completion: October 31, 2010
Contract Amount: $275,000
Approved Change Orders: $ 0
Revised Contract Amount: $275,000

Scope: The installation of a new modular unit for a convenience store for Auxiliary Services located in parking lot no. 12, near the Health Science Building.

store
Exterior view of convenience store looking east.



  VPA Complex – Theater Wing Re-Roof

Architect: DLR Group WWCOT
Construction Manager: Chaffey College
Contractor: Peterson Dean Roofing
Contract Start: May 21, 2010
Contract Completion: July 31, 2010
Original Contract: $148,700
Approved Change Orders: $0
Revised Contract: $148,700

Scope: Replacement of the existing roof on the two wings of the theater complex, to a new standing seam metal roof.

vpa roof
New standing seam roof.



  VPA North – Fire Lane

Architect: Associated Engineers
Construction Manager: Bernards
Contractor: ASR Constructors, Inc.
Contract Start: March 15, 2010
Contract Completion: April 28, 2010
Contract Amount: $ 135,000
Approved Change Orders: ($22,828)
Revised Contract Amount: $ 112,172

Scope: The project includes the renovation of the existing fire lane northeast of the EEC Building and south of the Language Arts Building. The project will rework existing contours of the fire lane, while connecting it to the new Visual and Performing Arts Complex fire lane in compliance with the Americans with Disabilities Act requirements.

fire lane
View looking west of the VPA North Fire Lane.



  Physical Education Facility-New Gymnasium

Architect: NTD Architecture
Construction Manager: Bernards
Contractor: Edge Development, Inc.
Contract Start: September 29, 2008
Contract Completion: December 23, 2009
Original Contract: $ 8,560,543
Approved Change Orders: $ 341,657
Revised Contract: $ 8,902,200

Scope: This project consists of a new 22,000 sq. ft. gymnasium. It will include locker rooms and a snack bar.

gym
Interior view of completed installation of wood flooring, bleachers, and scoreboard.




  Visual and Performing Arts Complex/
  Music Building

Architect: Hammel, Green & Abrahamson, Inc.
Construction Manager: Bernards
Contractor: ProWest Constructors
Contract Start: February 2008
Contract Completion:  
- Bldg. B & C- Ceramic Lab/Art Studio Summer 2009
- Bldg. F –Art Complex Fall 2009
- Bldg. E- Music Building Summer 2009
Original Contract: $ 22,145,000
Approved Change Orders: $ 1,175,619
Revised Contract: $ 23,320,619

Scope: This project is comprised of four buildings—two new buildings and two buildings that will be renovated. The Performing Arts building, the main building, will be a three-story structure. Including an art complex, digital media labs, photo studio, dance studio, and post-production lab, art studio, audio lab, interior design lab, lecture rooms, and faculty offices, this structure will be 46,000sq. ft. Additionally, there will be a 5,500 sq. ft. one-story music rehearsal building constructed. This will include instrumental and choral rooms. The two existing buildings will be renovated and modernized into a Ceramics lab and Fashion Art studio.

vpa rendering
Exterior of the Performing Arts Building-south side.




  Data and Telecom Cabling-VPA, New Gym,
  and Physical Science

Architect: P2S Engineering
Construction Manager: Bernards
Contractor: T & D Communications, Inc.
Contract Start: May 14, 2009
Contract Completion: November 6, 2009
Original Contract: $ 154,882
Approved Change Orders: $ ($5,127)
Revised Contract: $ 149,755

Scope: The Data and Telecom Cabling project involves the installation of new data and fiber cabling for the Visual and Performing Arts Complex, New Gymnasium, and the Physical Science Building. The work was separated into three (3) phases: Phase I-New cabling to the Fashion, Ceramics, and Music buildings in the Performing Arts Complex and the Physical Science Building; Phase II-New cabling to the Stadium Press Box and New Gymnasium; and Phase III-New cabling to the Performing Arts Building in the Performing Arts Complex.

suitomo
Completed installation of fiber optic cable in the Suitomo panel.



  Fontana Phase III-Parking Lot

Architect: HMC Architects
Construction Manager: Bernards
Contractor: Bogh Engineering, Inc.
Contract Start: May 11, 2009
Contract Completion: October 5, 2009
Original Contract: $ 1,089,000
Approved Change Orders: $ 42,618
Revised Contract: $ 1,131,618

Scope: The Fontana Phase III Parking Lot project consists of the construction of a new parking lot, landscaping, driveway/fire lanes, walkways, utilities, lighting, and signage at the Fontana Campus.

fontana lot
Bio-swale and walkway pavers installed



  Chino Health Science Parking Lot

Architect: MDA Johnson Favaro
Construction Manager: Chaffey College
Contractor: Laird Construction Co., Inc.
Contract Start: June 15, 2009
Contract Completion: August 15, 2009
Original Contract: $ 414,550
Approved Change Orders: $ 0
Revised Contract: $ 414,550

Scope: The construction of a 100,000 sq. ft. parking lot with 194 parking stalls south and west of the existing parking lots. The parking lot is adjacent to the existing Main Instructional Building located on the Chino Campus.

chino parking
Chino Campus parking lot, view looking west.



  Language Arts/Social Science-HVAC Project

Architect: P2S Engineering
Construction Manager: Bernards
Contractor: Siemens
Contract Start: May 15, 2009
Contract Completion: August 14, 2009
Original Contract: $ 2,700,000
Approved Change Orders: $ 103,828
Revised Contract: $ 2,803,828

Scope: Energy project upgrade to the Language Arts and Social Science buildings, which includes installation of new air handling equipment and new lighting systems.

sosci room
Social Science-Completed view of the classroom.



  Physical Science Complex-Roof Replacement

Architect: WWCOT Architect
Construction Manager: Chaffey College
Contractor: Cabral Roofing and Waterproofing Corp.
Contract Start: May 21, 2009
Contract Completion: July 17, 2009
Original Contract: $ 623,636
Approved Change Orders: $ 0
Revised Contract: $ 623,636

Scope: Replacement of the existing roof at the Physical Science building with a standing seam metal roof.


ps roof
Completed roof at the Physical Science building.



  Library Lawn/Fontana Phase II Landscaping

Architect: Steve Frenken Landscape Architecture
Construction Manager: Bernards
Contractor: Land Forms Landscape Construction
Contract Start: August 20, 2008
Contract Completion: November 25, 2008
Original Contract: $385,000
Approved Change Orders: ($450)
Revised Contract: $384,550

Scope: This project consists of landscaping and creating the irrigation system for the Fontana Campus Phase II project and the library lawn area at the Rancho Cucamonga campus.


     
fontana
Landscaping at the Fontana Campus.
  ancho cucamongarc campus
Landscaping at the Rancho Cucamonga Campus.



  Health and Life Science (HLS) Re-Roofing

Architect: WWCOT Architects
Construction Manager: Bernards
Contractor: Best Contracting Services, Inc.
Contract Start: January 1, 2008
Contract Completion: June 13, 2008
Original Contract: $456,169
Approved Change Orders: $16, 383
Revised Contract: $472,552

Scope: Comprised of the Health Science Building and the two Life Science buildings, the Health and Life Science Re-Roofing Project, consists of the removal of an existing built up roof on all three locations, and the construction of a new standing seam metal roof.


hls roof
Newly installed metal roof.



  Physical, Health, Life Science (PHLS) Renovations

Architect: WWCOT Architects
Construction Manager: Bernards
Contractor: PW Construction, Inc.
Contract Start: June 16, 2007
Contract Completion: Phase 1: June 18, 2008
Phase 2: August 15, 2008
Original Contract: $8,196,500
Approved Change Orders: $871,357
Revised Contract: $9,067,857

Scope: Comprised of 22,997 sq. ft., the Physical, Health, and Life Science Project consists of the renovation of five existing buildings.



dental
Completed dental lab at the Physical Science Building.



  New Marquee Sign

Architect: Hammel, Green & Abrahamson, Inc.
Construction Manager: Bernards
Contractor: Quiel Bros. Electric Sign
Contract Start: December 27, 2007
Contract Completion: June 2008
Original Contract: $180,000
Approved Change Orders: $1,500
Revised Contract: $181,500

Scope: Removal and replacement of the existing marquee sign located at the Haven Avenue entrance. The new marquee sign is a double-sided display board constructed of brushed aluminum and baked enamel surfaces.

marquee
New marquee sign at Haven Avenue.



  Parking Lot #12/Elevator

Architect: GKK Works
Construction Manager: Bernards
Contractor: Edge Development, Inc.
Contract Start: May 16, 2007
Contract Completion: November 11, 2007
Original Contract: 1,897,007
Approved Change Orders: $68,534
Revised Contract: $1,965,541

Scope: This project completely re-constructs Parking Lot 12 (Phase 1) including two accessible parking areas, sidewalks, lights and landscaping. An elevator (Phase 2) was also constructed connecting the VSS facility to Parking Lot 12.

elevator
Elevator tower and stairs leading to VSS.



Program Budget


   Program Fund Sources


sources


   Program Committed Costs


costs




Rev. 7/22/14


General Information | Student Resources | Instructional Programs | Campus Life | Community | Site Index | Home | MyChaffeyVIEW |

CHAFFEY COLLEGE • 5885 Haven Avenue, Rancho Cucamonga, CA 91737-3002 • 909/652-6000
Copyright 2014 Chaffey College. All rights reserved. Send technical questions to our Webmaster.


 
Back to Top