Chaffey College serves more than 20,000 students today. Through the Capitol Improvement Project the college will be able to provide education to the residents of the growing Inland Valley, more importantly, those seeking an education at Chaffey.


 
Latest News and Announcements

Construction Update

Chaffey College Measure L Citizens’ Oversight Committee


 
OVERVIEW


With the issuance of the first $47.7 million in construction bonds, Chaffey College began the first phase in the Capitol Improvement Project – Facilities Master Plan.

The Facilities Master Plan is funded by a general obligation bond, Measure L, passed by voters in the Chaffey Community College District on March 5, 2002.

The bond authorizes the college to issue up to $230 million in bonds during a 10 year period. A Citizen’s Oversight Committee meets each quarter to review the financial status and the construction progress. The committee issued the annual report to the community this summer.

The Chaffey College Facilities Master Plan consists of new construction, infrastructure repair, renovation and upgrades to existing facilities, and procurement of educational equipment. The Capitol Improvement Program has made significant progress. This is a summary of the completed projects and construction in progress.

 
CONSTRUCTION SCHEDULE


construction schedule

  Chaffey College
Administrative Services
5885 Haven Avenue
Rancho Cucamonga, CA 91737



image of ad and link to acrobat reader download




RECENTLY COMPLETED PROJECTS

Fontana, Phase II
Science Complex
Student Services / Administration
Educational Excellence Center
Fire Lane / Science Complex Lighting


CHINO INSTRUCTIONAL BUILDING

Architect: MDA Johnson Favaro
Contractor: Bernard Brothers, Inc.
Construction Manager: 3D/International; David Kannard
Contract Completion: 12/11/07

Scope

This two-story 55,000 SF facility will be the first building constructed on the new Chino Campus. The facility will consists of classrooms, science labs, computer labs, lecture halls, faculty offices and administration/student service space. The project also includes parking lots, hardscape, site lighting and utilities.

Status

The Contractor continues to make good progress on the exterior and interior of the building. The exterior sheathing is completed, waterproofing is underway, and the metal lath has recently started. Interior utilities are still in progress and drywall is being installed. The single ply roof system is completed.

chino 1   chino 2


CHINO COMMUNITY CENTER AND HEALTH SCIENCE

Architect: MDA Johnson Favaro
Contractor: EDGE Development
Construction Manager: 3D/International; David Kannard
Contract Completion: 11/8/08

Scope

This two-story 55,000 SF facility will be the first building constructed on the new Chino Campus. The facility will consists of classrooms, science labs, computer labs, lecture halls, faculty offices and administration/student service space. The project also includes parking lots, sidewalks, site lighting and utilities.

Status

The Contractor continues to make good progress on the exterior and interior of the building. The exterior sheathing is completed, waterproofing is underway, and the metal lath has recently started. Interior utilities are still in progress and drywall is being installed. The single ply roof system is completed.

chinohealth 1   chino 2


PHYSICAL, HEALTH, LIFE SCIENCES

Architect: WWCOT
Contractor: PW Construction
Construction Manager: 3D/International; Fernando Canon
Contract Completion: 8/15/08

Scope

This state-funded project consists of renovating the Health Sciences, Life Science East, Life Science West and Physical Science (SW) building and auditorium.

Status

Asbestos abatement and demolition is completed in all buildings except the Physical Science building. Under-slab utilities have been installed and the metal stud walls are being erected.

phls1   plhs2


PARKING LOT 12 / ELEVATOR

Architect: GKK
Contractor: EDGE Development
Construction Manager: 3D/International; Waleed Jouzy
Contract Completion: 11/11/07

Scope

This project will completely re-construct Parking Lot 12 (Phase 1) including two accessible parking areas, sidewalks, lights and landscaping. An elevator (Phase 2) will also be constructed connecting the VSS facility to Parking Lot 12.

Status

The new parking lot was completed and re-opened on August 17th. Work is still continuing with the lights and landscaping. The construction on the elevator is now underway and the footings have been poured.

parking1   parking2


SITE LIGHTING

Architect: P2S Engineering
Contractor: D&J Foothill Electric
Construction Manager: 3D/International; Daniel Lee

Scope

This project will provide new site lighting along the fire lane and within the Science Complex. Blue emergency phones are also being installed.

Status

Completed in mid-August. The lights are now fully operational.

lights1   lights2


FIRE LANE EXTENSION / ADA WALKWAYS

Architect: P2S Engineering
Contractor: 4Con
Construction Manager: 3D/International; Waleed Jouzy
Contract Completion: 12/15/07

Scope

This project will extend the fire lane up to Olive Way while providing an enhanced entry into the new Dr. Marie Kane Center. In addition, three new accessible ramps will be constructed connecting the fire lane to strategic locations on the Campus.

Status

Construction will begin on September 17.


PROJECTS IN BIDDING

Visual & Performing Arts – Construction is estimated to start in December 2007.

PROJECTS IN DESIGN

PE / Athletics
Campus Center
Business Education
Fiber Optic Infrastructure
EEC Access and Drainage
Chino Landscaping
Install Security Systems (Fontana, Science, SSA)

PROJECTS IN PLANNING

Omnitrans Transit Center
Skills Building Renovation
Storm Drainage System
Fontana, Phase III
ADA Master Plan
Chaffey College Marquee


l


 

MAINTENANCE YARD DRAINAGE

Architect: Wheeler and Gray
Contractor: 4-Con Engineering, Inc.
Construction Manager: Sarah Riley

Scope

Install storm drainage at the Maintenance and Operations yard.

Status

Request for filing of Notice of Completion is expected to be submitted for the October board meeting.

yard 1   yard 2
     
yard 3    


COLLEGE DRIVE LANDSCAPING

Architect: Steven Frenken and Associates
Contractor: Belaire-West Landscape, Inc.
Construction Manager: Sarah Riley

Scope

Grade, irrigate, and landscape College Drive. Plant palette has been recommended by Steve Frenken and the members of the “Tree Committee.”

Status

Construction is near completion, with Notice of Completion expected to be filed in September.

drive 1   drive 2
     
drive 3    


AGRICULTURAL DEMONSTRATION GARDEN

Architect: Steven Frenken and Associates
Contractor: MG Enterprizes
Construction Manager: Sarah Riley

Scope

Chaffey College has contracted for the soil preparation; grading of the area for grape vines, lemon and olive trees, and the installation of irrigation. Filippi Winery will do all planting, maintaining, and harvesting of the vines and trees. CCWD has provided a meter to provide free water for irrigation of the area.

Status

The project is nearing completion. Ongoing activities include trimming the vine stakes and the final stages of the fencing. Final walk through was scheduled August 2. Facilities expects to submit the Notice of Completion for October board meeting. MG Enterprizes is replacing dead trees, replacing crushed valve boxes, and reseeding where needed.

garden 1   garden 2
     
garden 3    


SKILLS ROAD IMPROVEMENT

Architect: Wheeler and Gray
Contractor: Excel Paving
Construction Manager: Sarah Riley

Scope

Removal of two parking spaces and extension of the curbing. This project incorporates the continuance of the fire lane above the Skills Building.

Status

Notice of Completion is going went to the board in August.

road 1   road 2
     
road 3    


POOL BOILER REPLACEMENT

Engineer: P2S
Contractor: Air-Ex Air Conditioning, Inc.
Construction Manager: Sarah Riley

Scope

Replacement of the pool boilers with more efficient equipment.

Status

The project began on August 15. Completion should be by mid September.


pool 1   pool 2
     
pool 3    


STADIUM PRESS BOX A/C

Engineer: P2S
Contractor: TBD
Construction Manager: Sarah Riley

Scope

Upgrading the existing air conditioning system in the Stadium Press Box

Status

Final drawings have been delivered to the college. Documents will be prepared to go to bid.

press 1   press 2


FONTANA LANDSCAPING

Architect: Steven Frenken and Associates
Contractor: TBD
Construction Manager: Sarah Riley

Scope

Complete landscaping and irrigation of the Ralph M. Lewis Center at the Fontana Campus.

Status

Original bids came in too high. The project is currently being rebid. Job walk was held September 11.

font 1   font 2
     
font 3    


GYMNASIUM LIGHTING UPGRADE

Architect: P2S Engineering
Contractor: TBD
Construction Manager: Sarah Riley

Scope

Provide upgraded lighting system to meet the current illumination requirements as set forth in the current IES standard.

Status

Documents have been prepared to go out to bid. Job walk is scheduled for September 18.

gym 1   gym 2
     
gym 3    


SSA-EEC-SCIENCE LANDSCAPING

Architect: Steven Frenken and Associates
Contractor: Southern California Landscaping
Construction Manager: Sarah Riley

Scope

Complete landscaping and irrigation for the Student Services Administration Building, the Educational Excellence Center, and the Science Complex.

Status

The Science Complex portion has been completed. The EEC area is currently under construction.

ssa 1   ssa 2
     
ssa 3    


PROJECTS IN DESIGN

projects


PROJECTS IN OBTAINING PROPOSAL PHASE/
DISCUSSION OF OPTIONS PHASE

CDC Playground Equipment Proposals
CDC Shade Structure Proposals
Handball Court Conversion for Storage Proposals
Child Development Center Red Mow Curb Proposals
Child Development Center Wrought Iron Fencing Proposals
Parking Lot 24 Wrought Iron Fencing Proposals
Dead Juniper Removal Proposals
Rat Proofing of the Aviary Proposals
Aviary Tie Down Relocation In Discussion
Aero Parking Lot In Discussion
Child Development Center Drainage In Discussion


SMALL PROJECTS CURRENTLY IN CONSTRUCTION
OR RECENTLY COMPLETED

Science Complex Water Feature In Construction
Human Resources Conference Room Shades In Construction
New Street Sign Installation In Construction
Asphalt Walkway below Business Education Building Completed
Video Screen installations at Wargin Hall Completed
110 Lighting Outlets in various buildings Completed
Temporary Parking Lot, Fontana Center Completed
Fontana Walkway Lighting Completed



Rev. 1/14/08