Chaffey College serves more than 20,000 students today. Through the Capitol Improvement Project the college will be able to provide education to the residents of the growing Inland Valley, more importantly, those seeking an education at Chaffey.
With the issuance of the first $47.7 million in construction
bonds, Chaffey College began the first phase in the Capitol Improvement
Project – Facilities
Master Plan.
The Facilities Master Plan is
funded by a general obligation bond, Measure L, passed by voters in the Chaffey
Community College District on March 5, 2002.
The bond authorizes the college to issue up to $230 million in
bonds during a 10 year period. A Citizen’s Oversight Committee meets
each quarter to review the financial status and the construction progress.
The committee issued the annual report to the community this summer.
The Chaffey College Facilities Master Plan consists of new construction,
infrastructure repair, renovation and upgrades to existing facilities, and
procurement of educational equipment.
The Capitol Improvement Program has made significant
progress. This is a summary of the completed projects and construction in
progress.
CONSTRUCTION SCHEDULE
Chaffey College
Administrative Services
5885 Haven Avenue
Rancho Cucamonga, CA 91737
RECENTLY COMPLETED PROJECTS
Fontana, Phase II
Science Complex
Student Services / Administration
Educational Excellence Center
Fire Lane / Science Complex Lighting
CHINO INSTRUCTIONAL BUILDING
Architect:
MDA Johnson Favaro
Contractor:
Bernard Brothers, Inc.
Construction Manager:
3D/International; David Kannard
Contract Completion:
12/11/07
Scope
This two-story 55,000 SF facility will be the first building constructed on the new
Chino Campus. The facility will consists of classrooms, science labs, computer labs,
lecture halls, faculty offices and administration/student service space. The project also
includes parking lots, hardscape, site lighting and utilities.
Status
The Contractor continues to make good progress on the exterior and interior of the
building. The exterior sheathing is completed, waterproofing is underway, and the metal
lath has recently started. Interior utilities are still in progress and drywall is being installed.
The single ply roof system is completed.
CHINO COMMUNITY CENTER AND HEALTH SCIENCE
Architect:
MDA Johnson Favaro
Contractor:
EDGE Development
Construction Manager:
3D/International; David Kannard
Contract Completion:
11/8/08
Scope
This two-story 55,000 SF facility will be the first building constructed on the new
Chino Campus. The facility will consists of classrooms, science labs, computer labs, lecture
halls, faculty offices and administration/student service space. The project also includes
parking lots, sidewalks, site lighting and utilities.
Status
The Contractor continues to make good progress on the exterior and interior of the
building. The exterior sheathing is completed, waterproofing is underway, and the metal
lath has recently started. Interior utilities are still in progress and drywall is being installed. The single ply roof system is completed.
PHYSICAL, HEALTH, LIFE SCIENCES
Architect:
WWCOT
Contractor:
PW Construction
Construction Manager:
3D/International; Fernando Canon
Contract Completion:
8/15/08
Scope
This state-funded project consists of renovating the Health Sciences, Life Science
East, Life Science West and Physical Science (SW) building and auditorium.
Status
Asbestos abatement and demolition is completed in all buildings except the
Physical Science building. Under-slab utilities have been installed and the metal stud walls
are being erected.
PARKING LOT 12 / ELEVATOR
Architect:
GKK
Contractor:
EDGE Development
Construction Manager:
3D/International; Waleed Jouzy
Contract Completion:
11/11/07
Scope
This project will completely re-construct Parking Lot 12 (Phase 1) including two
accessible parking areas, sidewalks, lights and landscaping. An elevator (Phase 2) will also
be constructed connecting the VSS facility to Parking Lot 12.
Status
The new parking lot was completed and re-opened on August 17th. Work is still
continuing with the lights and landscaping. The construction on the elevator is now
underway and the footings have been poured.
SITE LIGHTING
Architect:
P2S Engineering
Contractor:
D&J Foothill Electric
Construction Manager:
3D/International; Daniel Lee
Scope
This project will provide new site lighting along the fire lane and within the Science
Complex. Blue emergency phones are also being installed.
Status
Completed in mid-August. The lights are now fully operational.
FIRE LANE EXTENSION / ADA WALKWAYS
Architect:
P2S Engineering
Contractor:
4Con
Construction Manager:
3D/International; Waleed Jouzy
Contract Completion:
12/15/07
Scope
This project will extend the fire lane up to Olive Way while providing an enhanced
entry into the new Dr. Marie Kane Center. In addition, three new accessible ramps will be
constructed connecting the fire lane to strategic locations on the Campus.
Status
Construction will begin on September 17.
PROJECTS IN BIDDING
Visual & Performing Arts – Construction is estimated to start in December 2007.
PROJECTS IN DESIGN
PE / Athletics
Campus Center
Business Education
Fiber Optic Infrastructure
EEC Access and Drainage
Chino Landscaping
Install Security Systems (Fontana, Science, SSA)
PROJECTS IN PLANNING
Omnitrans Transit Center
Skills Building Renovation
Storm Drainage System
Fontana, Phase III
ADA Master Plan
Chaffey College Marquee
l
MAINTENANCE YARD DRAINAGE
Architect:
Wheeler and Gray
Contractor:
4-Con Engineering, Inc.
Construction Manager:
Sarah Riley
Scope
Install storm drainage at the Maintenance and Operations yard.
Status
Request for filing of Notice of Completion is expected to be submitted for the October board
meeting.
COLLEGE DRIVE LANDSCAPING
Architect:
Steven Frenken and Associates
Contractor:
Belaire-West Landscape, Inc.
Construction Manager:
Sarah Riley
Scope
Grade, irrigate, and landscape College Drive. Plant palette has been recommended by
Steve Frenken and the members of the “Tree Committee.”
Status
Construction is near completion, with Notice of Completion expected to be filed in
September.
AGRICULTURAL DEMONSTRATION GARDEN
Architect:
Steven Frenken and Associates
Contractor:
MG Enterprizes
Construction Manager:
Sarah Riley
Scope
Chaffey College has contracted for the soil preparation; grading of the area for grape
vines, lemon and olive trees, and the installation of irrigation. Filippi Winery will do all
planting, maintaining, and harvesting of the vines and trees. CCWD has provided a meter to
provide free water for irrigation of the area.
Status
The project is nearing completion. Ongoing activities include trimming the vine stakes
and the final stages of the fencing. Final walk through was scheduled August 2. Facilities
expects to submit the Notice of Completion for October board meeting. MG Enterprizes is
replacing dead trees, replacing crushed valve boxes, and reseeding where needed.
SKILLS ROAD IMPROVEMENT
Architect:
Wheeler and Gray
Contractor:
Excel Paving
Construction Manager:
Sarah Riley
Scope
Removal of two parking spaces and extension of the curbing. This project incorporates
the continuance of the fire lane above the Skills Building.
Status
Notice of Completion is going went to the board in August.
POOL BOILER REPLACEMENT
Engineer:
P2S
Contractor:
Air-Ex Air Conditioning, Inc.
Construction Manager:
Sarah Riley
Scope
Replacement of the pool boilers with more efficient equipment.
Status
The project began on August 15. Completion should be by mid September.
STADIUM PRESS BOX A/C
Engineer:
P2S
Contractor:
TBD
Construction Manager:
Sarah Riley
Scope
Upgrading the existing air conditioning system in the Stadium Press Box
Status
Final drawings have been delivered to the college. Documents will be prepared to go to
bid.
FONTANA LANDSCAPING
Architect:
Steven Frenken and Associates
Contractor:
TBD
Construction Manager:
Sarah Riley
Scope
Complete landscaping and irrigation of the Ralph M. Lewis Center at the Fontana
Campus.
Status
Original bids came in too high. The project is currently being rebid. Job walk was
held September 11.
GYMNASIUM LIGHTING UPGRADE
Architect:
P2S Engineering
Contractor:
TBD
Construction Manager:
Sarah Riley
Scope
Provide upgraded lighting system to meet the current illumination requirements as set
forth in the current IES standard.
Status
Documents have been prepared to go out to bid. Job walk is scheduled for September
18.
SSA-EEC-SCIENCE LANDSCAPING
Architect:
Steven Frenken and Associates
Contractor:
Southern California Landscaping
Construction Manager:
Sarah Riley
Scope
Complete landscaping and irrigation for the Student Services Administration Building,
the Educational Excellence Center, and the Science Complex.
Status
The Science Complex portion has been completed. The EEC area is currently under
construction.
PROJECTS IN DESIGN
PROJECTS IN OBTAINING PROPOSAL PHASE/
DISCUSSION OF OPTIONS PHASE
CDC Playground Equipment
Proposals
CDC Shade Structure
Proposals
Handball Court Conversion for Storage
Proposals
Child Development Center Red Mow Curb
Proposals
Child Development Center
Wrought Iron Fencing
Proposals
Parking Lot 24 Wrought Iron Fencing
Proposals
Dead Juniper Removal
Proposals
Rat Proofing of the Aviary
Proposals
Aviary Tie Down Relocation
In Discussion
Aero Parking Lot
In Discussion
Child Development Center Drainage
In Discussion
SMALL PROJECTS CURRENTLY IN CONSTRUCTION
OR RECENTLY COMPLETED