Chaffey Logo link

 
 




Construction Update

Chaffey College Measure L Citizens’ Oversight Committee

Latest News and Announcements


Download Reports

    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    December 2009
    November 2009
    October 2009
    September 2009
    August 2009
    July 2009
    June 2009
    May 2009
    April 2009
    March 2009
    February 2009
    January 2009

    December 2008


Construction Bid questions should be directed to 909/652-6701, or you can visit the construction bid page of the purchasing department site.


  bernards


construction update banner

Chaffey College serves more than 20,000 students today. Through the Capitol Improvement Project the college will be able to provide education to the residents of the growing Inland Valley, more importantly, those seeking an education at Chaffey.
Recent Completions | Under Construction | In Pre-Bid and Award | In Pre-Bid/Planning | Future Projects | Program Budget |

Overview


With the issuance of the first $47.7 million in construction bonds, Chaffey College began the first phase in the Capitol Improvement Project – Facilities Master Plan. The Facilities Master Plan is funded by a general obligation bond, Measure L, passed by voters in the Chaffey Community College District on March 5, 2002. The bond authorizes the college to issue up to $230 million in bonds during a 10 year period. A Citizen’s Oversight Committee meets each quarter to review the financial status and the construction progress. The Chaffey College Facilities Master Plan consists of new construction, infrastructure repair, renovation and upgrades to existing facilities, and procurement of educational equipment. The Capital Improvement Program has made significant progress. This is a summary of the completed projects and construction in progress.


Projects Under Construction


  Michael Alexander Campus Center

Architect: MDA Johnson Favaro
Construction Manager: Bernards
Contractor: See Multi-Prime Contracts
Contract Start: June 21, 2010
Contract Completion: July 31, 2011
Original Contract: $6,686,215
Approved Change Orders: $0
Revised Contract: $6,686,215
Multi-Prime Contracts (19): See Below
BP 01 – General Construction: USS Cal Builders, Inc. $ 648,000
BP 02 – Earthwork, Grading & Paving: Crew, Inc. 724,900
BP 03 – Concrete: ASR Constructors, Inc. 563,000
BP 04 – Masonry: ASR Constructors, Inc. 178,000
BP 05 – Structural Steel: KCB Towers, Inc. 574,290
BP 06 – Casework: K & Z Cabinet Co., Inc. 130,500
BP 07 – Roofing & Sheet Metal: Chapman Coast Roof Co., Inc. 220,449
BP 08 – Aluminum Storefront & Glazing: E & R Glass Contractors, Inc. 162,920
BP 09 – Framing, Drywall, Fireproofing, Lath & Plaster: Caston Plastering & Drywall, Inc. 685,585
BP 10 – Ceramic Tile: Continental Marble and Tile Company 74,104
BP 11 – Acoustical Ceilings: Commercial Interiors Acoustics, Inc. 44,998
BP 12 – Flooring: Donald M. Hoover Company 89,905
BP 13 – Painting: Triumph Painting 62,800
BP 14 – Plumbing: Nile ASR/Duke Constructors 451,000
BP 15 – HVAC: West-Tech Mechanical, Inc. 664,975
BP 16 – Electrical: Daniel's Electric Construction Co., Inc. 878,000
BP 17 – Landscape & Irrigation: Martinez Landscaping Co., Inc. 116,789
BP 18 – Fire Protection: JPI Development, Inc. 92,000
BP 19 – Kitchen Equipment: R.W. Smith & Co., Inc. 324,000

ccw
Rendering of exterior and landscaping.

Scope: Demolition of the existing Campus Center West Building and the construction of a new 16,400 sq. ft. two story Campus Center Building, including a student cafeteria, faculty dining room, health services, career services resource center, extended opportunity programs and services, and student government offices. Renovation of approximately 1,700 sq. ft. of the existing Campus Center East Building.

Status: The abatement of hazardous materials within the existing Campus Center West building is 90 percent complete. The temporary fence at the perimeter of the construction areas has been placed, and the capping off of utilities has begun. The demolition of the Campus Center West building, the landscape, and hardscape is scheduled to commence in July 2010.

     
ccw
Hazardous material abatement at Campus Center West.
  ccw
Removal of existing kitchen equipment.
     
ccw
Removal of materials from Campus Center West.
  ccw
Hazardous material abatement at Campus Center West.



  Omnitrans Transit Center

Architect: HMC Architects
Construction Manager: Bernards
Contractor: Young Contractors, Inc.
Contract Start: June 4, 2010
Contract Completion: October 31, 2010
Original Contract: $1,681,000
Approved Change Orders: $0
Revised Contract: $1,681,000

Scope: Design and construction of a new transit bus center for the loading and unloading of the Omnitrans buses on the Rancho Cucamonga campus.

Status: Young Contractors, Inc. has mobilized, and temporary fencing has been placed along College Drive. The existing asphalt paving material is being demolished, and will be placed as base material.

omnitrans
Map of the future Omnitrans Transit Center.
     
omnitrans
Demolition and removal of existing trees for future landscaping.
  omnitrans
Demolition of the existing asphalt parking lot.



  Physical Science Renovation

Architect: DLR Group WWCOT
Construction Manager: Bernards
Contractor: Southland Industries
Contract Start: June 1, 2010
Contract Completion: July 31, 2010
Original Contract: $2,094,591
Approved Change Orders: $0
Revised Contract: $2,094,591

Scope: This is an energy project services contract, which includes energy efficient lighting amd HVAC systems and controls, along with interior renovations.

Status: In the southeast quad, the framing and drywall installation is almost complete, and rough electrical and mechanical work is on gong. The forming for the concrete disabled ramp has begun in Parking Lot No. 11. In the northwest quad area, the framing of the walls is almost complete, and exterior work for the disabled ramp in Parking Lot No. 9 is ready to commence. Rough electrical and mechanical are on going.

physical science
Grading in preparation for the southeast disabled ramp.




  Math Success Center

Architect: DLR Group WWCOT
Construction Manager: Bernards
Contractor: Southland Industries
Contract Start: June 1, 2010
Contract Completion: July 31, 2010
Original Contract: $893,698
Approved Change Orders: $0
Revised Contract: $893,698

Scope: This is an energy project services contract, which includes energy efficient lighting amd HVAC systems and controls, along with interior renovations.

Status: Demolition activities are complete, and electrical and mechanical work is on going in the ceilings. Wall framing has begun.

math sc
Interior view of over head mechancial installation.




  VPA Complex – Theater Wing Re-Roof

Architect: DLR Group WWCOT
Construction Manager: Chaffey College
Contractor: Peterson Dean Roofing
Contract Start: May 21, 2010
Contract Completion: July 31, 2010
Original Contract: $148,700
Approved Change Orders: $0
Revised Contract: $148,700

Scope: Replacement of the existing roof on the two wings of the theater complex, to a new standing seam metal roof.

Status: The existing roof has been removed, and the new underlayment, gutters, and sheet metal are being installed.

vpa roof
Installation of sheet metal on the lower west roof of the theater.



  VPA Landscape Addition

Architect: Soltis Landscape Services
Construction Manager: Bernards
Contractor: Elite Landscaping, Inc.
Contract Start: April 19, 2010
Contract Completion: July 16, 2010
Contract Amount: $ 247,770
Approved Change Orders: $ 0
Revised Contract Amount: $ 247,770

Scope: The project includes the landscaping and irrigation of the areas adjacent to the Visual and Performing Arts Complex.

Status: Elite Landscaping, Inc. has completed boulder placement, and is placing the stone mulch and 'Chaffey Gold' gravel. Tree and shrub placement and planting are on going. Bark mulch will be placed early July 2010. The installation of lateral lines and bubbler systems is on going. The forming and placement of the concrete footings for the benches and new swale is scheduled to begin July 2010.

landscape
View of the 911 memorial fountain, 'Chaffey Gold' gravel, and future seating area, looking southwest.



  Fontana Phase III-Academic Building

Architect: HMC Architects
Construction Manager: Bernards
Contractor: See Multi-Prime Contracts
Contract Start: March 16, 2010
Contract Completion: April 23, 2011
Original Contract: $ 7,305,036
Approved Change Orders: $ 0
Revised Contract: $ 7,305,036
Multi-Prime Contracts (17): See Below
FABP 01 – General Construction: ISEC, Inc. $ 568,259
FABP 02 – Earthwork, Grading & Paving: Crew, Inc. 188,000
FABP 03 – Concrete: Rossi Concrete, Inc. 529,000
FABP 04 – Fire Protection: Kincaid Industries, Inc. 161,000
FABP 05 – Structural, Misc. Steel & Metal Decking: Columbia Steel, Inc. 646,800
FABP 06 – Casework & Millwork: ISEC, Inc. 234,937
FABP 07 – Roofing & Sheet Metal: Waterproofing Experts, Inc. 516,546
FABP 08 – Aluminum Storefront & Glazing: Best Contracting Services, Inc. 571,184
FABP 09 – Framing, Drywall, Fireproofing, Lath & Plaster: Caston Plastering & Drywall, Inc. 965,585
FABP 10 – Ceramic Tile: J. Colavin & Son, Inc. 54,850
FABP 11 – Acoustical Ceilings: KHS&S Contractors, Inc. 85,483
FABP 12 – Flooring: Donald M. Hoover Company 122,000
FABP 13 – Painting: AJ Fistes Corporation 69,792
FABP 14 – Plumbing: Nile Advanced Construction, Inc. 398,600
FABP 15 – HVAC: West-Tech Mechanical, Inc. 910,000
FABP 16 – Electrical: R.I.S. Electrical Contractors, Inc. 1,177,000
FABP 17 – Landscape & Irrigation: ASR Constructors, Inc. 106,000

Scope: Comprised of 30,400 sq ft., this will be a new academic building. Inside the building, there will be four classrooms, two labs with prep rooms, a library, a bookstore, student lounge, dance studio, and administration offices.

Status: Building footings are complete, and the forms have been stripped. Forming and placement of the elevator pit walls, under slab electrical and plumbing, is scheduled to commence the first week of July 2010.

fontana
Exterior rendering of the building looking north.

fontana
Forming of rebar for footings.


fontana
58 meter concrete pump placing concrete.

     
fontana
Placement of concrete footings.
  fontana
Slab and footing preparation.



  Physical Education Facility - Gymnasium Renovation

Architect: NTD Architecture
Construction Manager: Bernards
Contractor: USS Cal Builders, Inc.
Contract Start: February 1, 2010
Contract Completion: October 31, 2010
Original Contract: $ 4,694,000
Approved Change Orders: $ 0
Revised Contract: $ 4,694,000

Scope: Renovation of the 30,843 sq. ft. existing athletics building.

Status: The asphalt in parking lot no. 15 has been demolished and removed. USS Cal Builders, Inc. has installed glazing on the mezzanine level fitness lab and first floor faculty offices. Drywall, metal stud framing, and overhead mechanical, electrical, and plumbing are on going. Installation of HVAC is on going, and the air handling unit hatches have been delivered. Forming for the shower curbs is complete, and will be placed in early July 2010.

gym
Metal stud framing and curb placement for lockers in the team locker room.
     
gym
Placement of new glazing on the mezzanine level fitness lab.
  gym
Demolition of the existing asphalt parking lot.
     
gym
Forming of rebar in preparation for concrete locker curbs in the mens' and womens' locker rooms.
   



Projects in Bid and Award



Projects in Pre-Bid/Planning

Measure “L” Build Out Future Projects


   Business Education Renovation

Status: This project is in design development.
Architect: DLR Group WWCOT

   Aviary Landscape

Status: This project is in preparation for the bid and award phase.
Architect: Soltis Landscape Services

   SSA-East Door Entrances

Status: This project is awaiting DSA approval.
Architect: HMC Architects

   PE Athletics-Parking Lot and Flagpole

Status: This project is in design development.
Engineer: Associated Engineers

   Fire Alarm-Campus Center East, IT, & Planetarium

Status: This project is in design development.
Engineer: P2S Engineering, Inc.


   Central Plant Build-Out

Status: This project is scheduled as an energy project and is in design development.
Engineer: P2S Engineering, Inc.

   Liberal Arts and Letters

Status: Awaiting approval of the State funding proposal pending passage of the State Revenue Bond measure.

   Library Remodel / Expansion

Status: Awaiting approval of the State funding proposal pending passage of the State Revenue Bond measure.

   EEC/Museum – ADA Access and Drainage

Status: The project is in design development.
Architect: DLR Group WWCOT



Projects Completed


  VPA North – Fire Lane

Architect: Associated Engineers
Construction Manager: Bernards
Contractor: ASR Constructors, Inc.
Contract Start: March 15, 2010
Contract Completion: April 28, 2010
Contract Amount: $ 135,000
Approved Change Orders: ($22,828)
Revised Contract Amount: $ 112,172

Scope: The project includes the renovation of the existing fire lane northeast of the EEC Building and south of the Language Arts Building. The project will rework existing contours of the fire lane, while connecting it to the new Visual and Performing Arts Complex fire lane in compliance with the Americans with Disabilities Act requirements.

fire lane
View looking west of the VPA North Fire Lane.



  Physical Education Facility-New Gymnasium

Architect: NTD Architecture
Construction Manager: Bernards
Contractor: Edge Development, Inc.
Contract Start: September 29, 2008
Contract Completion: December 23, 2009
Original Contract: $ 8,560,543
Approved Change Orders: $ 341,657
Revised Contract: $ 8,902,200

Scope: This project consists of a new 22,000 sq. ft. gymnasium. It will include locker rooms and a snack bar.

gym
Interior view of completed installation of wood flooring, bleachers, and scoreboard.




  Visual and Performing Arts Complex/Music Building

Architect: Hammel, Green & Abrahamson, Inc.
Construction Manager: Bernards
Contractor: ProWest Constructors
Contract Start: February 2008
Contract Completion:  
- Bldg. B & C- Ceramic Lab/Art Studio Summer 2009
- Bldg. F –Art Complex Fall 2009
- Bldg. E- Music Building Summer 2009
Original Contract: $ 22,145,000
Approved Change Orders: $ 1,175,619
Revised Contract: $ 23,320,619

Scope: This project is comprised of four buildings—two new buildings and two buildings that will be renovated. The Performing Arts building, the main building, will be a three-story structure. Including an art complex, digital media labs, photo studio, dance studio, and post-production lab, art studio, audio lab, interior design lab, lecture rooms, and faculty offices, this structure will be 46,000sq. ft. Additionally, there will be a 5,500 sq. ft. one-story music rehearsal building constructed. This will include instrumental and choral rooms. The two existing buildings will be renovated and modernized into a Ceramics lab and Fashion Art studio.

vpa rendering
Exterior of the Performing Arts Building-south side.




  Data and Telecom Cabling-VPA, New Gym, & Physical Science

Architect: P2S Engineering
Construction Manager: Bernards
Contractor: T & D Communications, Inc.
Contract Start: May 14, 2009
Contract Completion: November 6, 2009
Original Contract: $ 154,882
Approved Change Orders: $ ($5,127)
Revised Contract: $ 149,755

Scope: The Data and Telecom Cabling project involves the installation of new data and fiber cabling for the Visual and Performing Arts Complex, New Gymnasium, and the Physical Science Building. The work was seperated into three (3) phases: Phase I-New cabling to the Fashion, Ceramics, and Music buildings in the Performing Arts Complex and the Physical Science Building; Phase II-New cabling to the Stadium Press Box and New Gymnasium; and Phase III-New cabling to the Performing Arts Building in the Performing Arts Complex.

suitomo
Completed installation of fiber optic cable in the Suitomo panel.



  Fontana Phase III-Parking Lot

Architect: HMC Architects
Construction Manager: Bernards
Contractor: Bogh Engineering, Inc.
Contract Start: May 11, 2009
Contract Completion: October 5, 2009
Original Contract: $ 1,089,000
Approved Change Orders: $ 42,618
Revised Contract: $ 1,131,618

Scope: The Fontana Phase III Parking Lot project consists of the construction of a new parking lot, landscaping, driveway/fire lanes, walkways, utilities, lighting, and signage at the Fontana Campus.

fontana lot
Bio-swale and walkway pavers installed



  Chino Health Science Parking Lot

Architect: MDA Johnson Favaro
Construction Manager: Chaffey College
Contractor: Laird Construction Co., Inc.
Contract Start: June 15, 2009
Contract Completion: August 15, 2009
Original Contract: $ 414,550
Approved Change Orders: $ 0
Revised Contract: $ 414,550

Scope: The construction of a 100,000 sq. ft. parking lot with 194 parking stalls south and west of the existing parking lots.The parking lot is adjacent to the existing Main Instructional Building located on the Chino Campus.

chino parking
Chino Campus parking lot, view looking west.



  Language Arts/Social Science-HVAC Project

Architect: P2S Engineering
Construction Manager: Bernards
Contractor: Siemens
Contract Start: May 15, 2009
Contract Completion: August 14, 2009
Original Contract: $ 2,700,000
Approved Change Orders: $ 103,828
Revised Contract: $ 2,803,828

Scope: Energy project upgrade to the Language Arts and Social Science buildings, which includes installation of new air handling equipment and new lighting systems.

sosci room
Social Science-Completed view of the classroom.



  Physical Science Complex-Roof Replacement

Architect: WWCOT Architect
Construction Manager: Chaffey College
Contractor: Cabral Roofing and Waterproofing Corp.
Contract Start: May 21, 2009
Contract Completion: July 17, 2009
Original Contract: $ 623,636
Approved Change Orders: $ 0
Revised Contract: $ 623,636

Scope: Replacement of the existing roof at the Physical Science building with a standing seam metal roof.


ps roof
Completed roof at the Physical Science building.



  Library Lawn/Fontana Phase II Landscaping

Architect: Steve Frenken Landscape Architecture
Construction Manager: Bernards
Contractor: Land Forms Landscape Construction
Contract Start: August 20, 2008
Contract Completion: November 25, 2008
Original Contract: $385,000
Approved Change Orders: ($450)
Revised Contract: $384,550

Scope: This project consists of landscaping and creating the irrigation system for the Fontana Campus Phase II project and the library lawn area at the Rancho Cucamonga campus.


     
fontana
Landscaping at the Fontana Campus.
  ancho cucamongarc campus
Landscaping at the Rancho Cucamonga Campus.



  Health and Life Science (HLS) Re-Roofing

Architect: WWCOT Architects
Construction Manager: Bernards
Contractor: Best Contracting Services, Inc.
Contract Start: January 1, 2008
Contract Completion: June 13, 2008
Original Contract: $456,169
Approved Change Orders: $16, 383
Revised Contract: $472,552

Scope: Comprised of the Health Science Building and the two Life Science buildings, the Health and Life Science Re-Roofing Project, consists of the removal of an existing built up roof on all three locations, and the construction of a new standing seam metal roof.


hls roof
Newly installed metal roof.



  Physical, Health, Life Science (PHLS) Renovations

Architect: WWCOT Architects
Construction Manager: Bernards
Contractor: PW Construction, Inc.
Contract Start: June 16, 2007
Contract Completion: Phase 1: June 18, 2008
Phase 2: August 15, 2008
Original Contract: $8,196,500
Approved Change Orders: $871,357
Revised Contract: $9,067,857

Scope: Comprised of 22,997 sq. ft., the Physical, Health, and Life Science Project consists of the renovation of five existing buildings.



dental
Completed dental lab at the Physical Science Building.



  New Marquee Sign

Architect: Hammel, Green & Abrahamson, Inc.
Construction Manager: Bernards
Contractor: Quiel Bros. Electric Sign
Contract Start: December 27, 2007
Contract Completion: June 2008
Original Contract: $180,000
Approved Change Orders: $1,500
Revised Contract: $181,500

Scope: Removal and replacement of the existing marquee sign located at the Haven Avenue entrance. The new marquee sign is a double-sided display board constructed of brushed aluminum and baked enamel surfaces.

marquee
New marquee sign at Haven Avenue.



  Parking Lot #12/Elevator

Architect: GKK Works
Construction Manager: Bernards
Contractor: Edge Development, Inc.
Contract Start: May 16, 2007
Contract Completion: November 11, 2007
Original Contract: 1,897,007
Approved Change Orders: $68,534
Revised Contract: $1,965,541

Scope: This project completely re-constructs Parking Lot 12 (Phase 1) including two accessible parking areas, sidewalks, lights and landscaping. An elevator (Phase 2) was also constructed connecting the VSS facility to Parking Lot 12.

elevator
Elevator tower and stairs leading to VSS.



Program Budget


   Program Fund Sources


sources


   Program Committed Costs


costs




Rev. 8/4/10


General Information | Student Resources | Instructional Programs | Campus Life | Community | Site Index | Home | MyChaffeyVIEW |

CHAFFEY COLLEGE • 5885 Haven Avenue, Rancho Cucamonga, CA 91737-3002 • 909/652-6000
Copyright 2010 Chaffey College. All rights reserved. Send technical questions to our Webmaster.


 
Back to Top