Construction Bid questions should be directed to
909/652-6701, or you can visit the construction bid page of the purchasing department site.
Chaffey College serves more than 20,000 students today. Through the Capitol Improvement Project the college will be able to provide education to the residents of the growing Inland Valley, more importantly, those seeking an education at Chaffey.
With the issuance of the first $47.7 million in construction
bonds, Chaffey College began the first phase in the Capitol Improvement
Project – Facilities
Master Plan. The Facilities Master Plan is
funded by a general obligation bond, Measure L, passed by voters in the Chaffey
Community College District on March 5, 2002.
The bond authorizes the college to issue up to $230 million in
bonds during a 10 year period. A Citizen’s Oversight Committee meets
each quarter to review the financial status and the construction progress.
The Chaffey College Facilities Master Plan consists of new construction,
infrastructure repair, renovation and upgrades to existing facilities, and
procurement of educational equipment.
The Capital Improvement Program has made significant
progress. This is a summary of the completed projects and construction in
progress.
Projects Under Construction
Athletic Field Parking Lot and Flagpole
Engineer:
Associated Engineers
Construction Manager:
Chaffey College
Contractor:
Laird Construction Company, Inc.
Contract Start:
October 5, 2012
Contract Completion:
January 15, 2013
Original Contract:
$697,000
Approved Change Orders:
$26,966
Revised Contract:
$723,966
Scope:The project includes the construction of a new
116,000 square foot, 260-space decomposed granite
parking lot to serve the needs of adjacent athletic
fields.
Status: The parking lot is open for use, and the
contractor is working on final closeout items.
Completed installation of decomposed granite, Code
Blue phones, and light poles facing southeast.
Projects in Bid and Award Projects in Pre-Bid/Planning Measure “L” Build Out Future Projects
Central Plant Build-Out – Phase 1C – TES Tank
Status: The project includes the construction of a new thermal energy storage tank and addition of six
boilers at the Central Plant, and has been approved by the Division of the State Architect (DSA).
Construction is tentatively scheduled to begin in spring 2013. Architect: P2S Engineering, Inc.
Liberal Arts and Letters
Status: The project is awaiting approval of the State funding proposal, pending passage of the State
Revenue Bond measure.
Library Remodel / Expansion
Status: The project is awaiting approval of the State funding proposal, pending passage of the State
Revenue Bond measure.
Projects Completed
North Parking Lot - Catch Basin Addition
Engineer:
Fuscoe Engineering, Inc.
Construction Manager:
Bernards
Contractor:
Excel Paving Company
Contract Start:
July 2, 2012
Contract Completion:
August 3, 2012
Original Contract:
$127,965
Approved Change Orders:
$0
Revised Contract:
$127,965
Scope: The project includes the addition of drainage
systems at Parking Lot 4 to address storm drain
overflow.
View of completed catch basin installation at
Parking Lot 4 facing east.
Health Science Pathway
Engineer:
Fuscoe Engineering, Inc.
Construction Manager:
Bernards
Contractor:
Laird Construction/KAR Construction
Ryko Construction/Raffi's Metal Design
Contract Start:
March 19, 2012
Contract Completion:
May 31, 2012
Original Contract:
$121,832
Approved Change Orders:
$6,123
Revised Contract:
$127,955
Scope: Addition of a concrete pathway from Health Sciences to the Michael Alexander Campus Center.
View of completed pathway facing northeast.
Greenhouse
Engineer:
P2S Engineering, Inc.
Construction Manager:
Chaffey College
Contractor:
Cavalier Construction/VO Builders
Contract Start:
September 14, 2011
Contract Completion:
April 30, 2012
Original Contract:
$148,000
Approved Change Orders:
($216)
Revised Contract:
$147,784
Scope: Installation of a prefabricated greenhouse
structure at the Science Complex.
View of completed structure and concrete walkway.
Omnitrans – Media Plan
Construction Manager:
Bernards
Contractor:
Daniel's Electric Construction, Inc.
Black Box Network Services/Siemens
Contract Start:
November 1, 2011
Contract Completion:
January 31, 2012
Original Contract:
$71,354
Approved Change Orders:
$0
Revised Contract:
$71,354
Scope: Addition of security cameras and electrical
upgrades in the Omnitrans parking lot.
New security camera installed on light pole at the
Omnitrans parking lot.
Michael Alexander Campus Center
Architect:
MDA Johnson Favaro
Construction Manager:
Bernards
Contractor:
See Multi-Prime Contracts
Contract Start:
June 21, 2010
Contract Completion:
August 11, 2011
Original Contract:
$6,686,215
Approved Change Orders:
$216,370
Revised Contract:
$6,902,585
Multi-Prime Contracts (19):
See Below
BP 01 – General Construction: USS Cal Builders, Inc.
$ 643,536
BP 02 – Earthwork, Grading & Paving: Crew, Inc.
774,048
BP 03 – Concrete: ASR Constructors, Inc.
567,496
BP 04 – Masonry: ASR Constructors, Inc.
178,000
BP 05 – Structural Steel: KCB Towers, Inc.
574,290
BP 06 – Casework: K & Z Cabinet Co., Inc.
134,531
BP 07 – Roofing & Sheet Metal: Chapman Coast Roof Co., Inc.
220,449
BP 08 – Aluminum Storefront & Glazing: E & R Glass Contractors, Inc.
167,868
BP 09 – Framing, Drywall, Fireproofing, Lath & Plaster: Caston Plastering & Drywall, Inc.
698,372
BP 10 – Ceramic Tile: Continental Marble and Tile Company
74,104
BP 11 – Acoustical Ceilings: Commercial Interiors Acoustics, Inc.
47,315
BP 12 – Flooring: Donald M. Hoover Company
95,998
BP 13 – Painting: Triumph Painting
65,626
BP 14 – Plumbing: Nile ASR/Duke Constructors
467,902
BP 15 – HVAC: West-Tech Mechanical, Inc.
674,289
BP 16 – Electrical: Daniel's Electric Construction Co., Inc.
927,339
BP 17 – Landscape & Irrigation: Martinez Landscaping Co., Inc.
147,939
BP 18 – Fire Protection: JPI Development, Inc.
92,695
BP 19 – Kitchen Equipment: R.W. Smith & Co., Inc.
350,688
Aerial view of the completed building facing northeast.
Scope: Demolition of the existing Campus Center West Building and the construction of a new 16,400
sq. ft. two story Campus Center Building, including a student cafeteria, faculty dining room, health
services, career services resource center, extended opportunity programs and services, and student
government offices. Renovation of approximately 1,700 sq. ft. of the existing Campus Center East
Building.
Completed student dining area at first floor.
Omnitrans – Roadway Work
Construction Manager:
Bernards
Contractor:
Mission Paving and Sealing, Inc.
Contract Start:
December 19, 2011
Contract Completion:
January 16, 2012
Original Contract:
$89,985
Approved Change Orders:
$0
Revised Contract:
$89,985
Scope: Additional road and parking lot work at College
Drive.
Completion of asphalt placement and striping at
College Drive.
Business Education Renovation
Architect:
DLR Group WWCOT
Construction Manager:
Bernards
Contractor:
Southland Industries, Inc.
Contract Start:
May 31, 2011
Contract Completion:
August 7, 2011
Original Contract:
$3,155,168
Approved Change Orders:
$212,371
Revised Contract:
$3,367,539
Scope: Energy upgrades, along with interior and exterior renovations, of the Business Education
building.
Completed installation of furniture and equipment at renovated classroom.
Fontana Phase III-Academic Building
Architect:
HMC Architects
Construction Manager:
Bernards
Contractor:
See Multi-Prime Contracts
Contract Start:
March 16, 2010
Contract Completion:
June 24, 2011
Original Contract:
$ 7,305,036
Approved Change Orders:
$ 533,970
Revised Contract:
$ 7,839,006
Multi-Prime Contracts (17):
See Below
FABP 01 – General Construction: ISEC, Inc.
$ 621,073
FABP 02 – Earthwork, Grading & Paving: Crew, Inc.
200,216
FABP 03 – Concrete: Rossi Concrete, Inc.
561,334
FABP 04 – Fire Protection: Kincaid Industries, Inc.
167,131
FABP 05 – Structural, Misc. Steel & Metal Decking: Columbia Steel, Inc.
665,962
FABP 06 – Casework & Millwork: ISEC, Inc.
257,679
FABP 07 – Roofing & Sheet Metal: Waterproofing Experts, Inc.
523,021
FABP 08 – Aluminum Storefront & Glazing: Best Contracting Services, Inc.
FABP 11 – Acoustical Ceilings: KHS&S Contractors, Inc.
100,764
FABP 12 – Flooring: Donald M. Hoover Company
167,415
FABP 13 – Painting: AJ Fistes Corporation
92,507
FABP 14 – Plumbing: Nile Advanced Construction, Inc.
398,600
FABP 15 – HVAC: West-Tech Mechanical, Inc.
940,651
FABP 16 – Electrical: R.I.S. Electrical Contractors, Inc.
1,389,997
FABP 17 – Landscape & Irrigation: ASR Constructors, Inc.
149,660
Scope: Comprised of 30,400 sq ft., this will be a new academic building. Inside the building, there will be four classrooms, two labs with prep rooms, a library, a bookstore, student lounge, dance studio, and administration offices.
Building exterior facing southeast.
Completed casework and fixture installation at
laboratory.
Fire Alarm Upgrades
Architect:
P2S Engineering, Inc.
Construction Manager:
Chaffey College
Contractor:
Siemens Industry, Inc.
Contract Start:
April 18, 2011
Contract Completion:
November 3, 2011
Original Contract:
$193,141
Approved Change Orders:
$0
Revised Contract:
$193,141
Scope: Upgrade and redesign of existing fire alarm
systems at the Campus Center East, Information
Services, and Planetarium buildings.
Installation of upgraded fire alarm at Information
Services.
Student Services and Administration
East Entrance Doors
Architect:
HMC Architects
Construction Manager:
Chaffey College
Contractor:
Daniel's Electric/E & R Glass
Contract Start:
September 8, 2011
Contract Completion:
October 31, 2011
Original Contract:
$73,000
Approved Change Orders:
$1,805
Revised Contract:
$74,805
Scope: Installation of an automatic sliding door and
upgrades to existing doors at the Student
Services/Administration building.
Completed door installation at east entrance to
the Student Services and Administration building.
Scope: Renovation of the 30,843 sq. ft. existing athletics building.
New resilient wood flooring and striping at the main
gymnasium floor.
Completed ceramic tile, mirrors, plumbing fixtures,
and partitions at the men's restroom.
Central Plant Build Out-Hot Water Upgrade
Architect:
P2S Engineering, Inc.
Construction Manager:
Bernards
Contractor:
Hickman Mechanical, Inc.
Contract Start:
October 27, 2010
Contract Completion:
February 11, 2011
Contract Amount:
$ 148,800
Approved Change Orders:
$ 12,234
Revised Contract Amount:
$ 161,034
Scope: The project consists of upgrades to the
existing boiler system and expansion tanks at the
Central Plant-Phase One.
Interior view of retrofitted boilers.
Aviary Landscape
Architect:
Soltis Landscape Services, Inc.
Construction Manager:
Chaffey College
Contractor:
Nature Tech Landscape
Contract Start:
September 15, 2010
Contract Completion:
February 22, 2011
Contract Amount:
$ 105,000
Approved Change Orders:
$ 10,210
Revised Contract Amount:
$ 115,210
Scope: The installation of landscape within the
Aviary structure.
Completed habitat installation and landscaping looking south.
Omnitrans Transit Center
Architect:
HMC Architects
Construction Manager:
Bernards
Contractor:
Young Contractors, Inc.
Contract Start:
June 4, 2010
Contract Completion:
November 24, 2010
Original Contract:
$1,681,000
Approved Change Orders:
$84,738
Revised Contract:
$1,765,738
Scope: Design and construction of a new transit bus center for the loading and unloading of the Omnitrans buses on the Rancho Cucamonga campus.
Completed bus shelter looking west.
VPA Landscape Addition
Architect:
Soltis Landscape Services
Construction Manager:
Bernards
Contractor:
Elite Landscaping, Inc.
Contract Start:
April 19, 2010
Contract Completion:
December 12, 2010
Contract Amount:
$ 247,770
Approved Change Orders:
$ 10,337
Revised Contract Amount:
$ 258,107
Scope: The project includes the landscaping and
irrigation of the areas adjacent to the Visual and
Performing Arts Complex.
New rock swale and shrubs at tree alley, south of the
Center for the Arts building.
Physical Science Renovation
Architect:
DLR Group WWCOT
Construction Manager:
Bernards
Contractor:
Southland Industries
Contract Start:
June 1, 2010
Contract Completion:
July 31, 2010
Original Contract:
$ 2,094,591
Approved Change Orders:
$ 160,201
Revised Contract:
$ 2,254,792
Scope: This is an energy project services contract, which includes energy efficient lighting amd HVAC systems and controls, along with interior renovations.
Interior view of completed classroom, and lighting upgrades.
Math Success Center
Architect:
DLR Group WWCOT
Construction Manager:
Bernards
Contractor:
Southland Industries
Contract Start:
June 1, 2010
Contract Completion:
July 31, 2010
Original Contract:
$ 893,698
Approved Change Orders:
$ 14,908
Revised Contract:
$ 908,606
Scope: This is an energy project services contract, which includes energy efficient lighting amd HVAC systems and controls, along with interior renovations.
Interior view of completed lighting upgrades and classroom.
Panther Express Convenience Store
Architect:
HMC Architects
Construction Manager:
Bernards
Contractor:
KAR Construction/Mobile Modular
Contract Start:
July 26, 2010
Contract Completion:
October 31, 2010
Contract Amount:
$275,000
Approved Change Orders:
$ 0
Revised Contract Amount:
$275,000
Scope: The installation of a new modular unit for a convenience store for Auxiliary Services located in parking lot no. 12, near the Health Science Building.
Exterior view of convenience store looking east.
VPA Complex – Theater Wing Re-Roof
Architect:
DLR Group WWCOT
Construction Manager:
Chaffey College
Contractor:
Peterson Dean Roofing
Contract Start:
May 21, 2010
Contract Completion:
July 31, 2010
Original Contract:
$148,700
Approved Change Orders:
$0
Revised Contract:
$148,700
Scope: Replacement of the existing roof on the two wings of the theater complex, to a new standing seam metal roof.
New standing seam roof.
VPA North – Fire Lane
Architect:
Associated Engineers
Construction Manager:
Bernards
Contractor:
ASR Constructors, Inc.
Contract Start:
March 15, 2010
Contract Completion:
April 28, 2010
Contract Amount:
$ 135,000
Approved Change Orders:
($22,828)
Revised Contract Amount:
$ 112,172
Scope: The project includes the renovation of the existing fire lane northeast of the EEC Building and south of the Language Arts Building. The project will rework existing contours of the fire lane, while connecting it to the new Visual and Performing Arts Complex fire lane in compliance with the Americans with Disabilities Act requirements.
View looking west of the VPA North Fire Lane.
Physical Education Facility-New Gymnasium
Architect:
NTD Architecture
Construction Manager:
Bernards
Contractor:
Edge Development, Inc.
Contract Start:
September 29, 2008
Contract Completion:
December 23, 2009
Original Contract:
$ 8,560,543
Approved Change Orders:
$ 341,657
Revised Contract:
$ 8,902,200
Scope: This project consists of a new 22,000 sq. ft. gymnasium. It will include locker rooms and a snack bar.
Interior view of completed installation of wood
flooring, bleachers, and scoreboard.
Visual and Performing Arts Complex/
Music Building
Architect:
Hammel, Green & Abrahamson, Inc.
Construction Manager:
Bernards
Contractor:
ProWest Constructors
Contract Start:
February 2008
Contract Completion:
- Bldg. B & C- Ceramic Lab/Art Studio
Summer 2009
- Bldg. F –Art Complex
Fall 2009
- Bldg. E- Music Building
Summer 2009
Original Contract:
$ 22,145,000
Approved Change Orders:
$ 1,175,619
Revised Contract:
$ 23,320,619
Scope: This project is comprised of four buildings—two new buildings and two buildings that will be renovated. The Performing Arts building, the main building, will be a three-story structure. Including an art complex, digital media labs, photo studio, dance studio, and post-production lab, art studio, audio lab, interior design lab, lecture rooms, and faculty offices, this structure will be 46,000sq. ft. Additionally, there will be a 5,500 sq. ft. one-story music rehearsal building constructed. This will include instrumental and choral rooms. The two existing buildings will be renovated and modernized into a Ceramics lab and Fashion Art studio.
Exterior of the Performing Arts Building-south
side.
Data and Telecom Cabling-VPA, New Gym,
and Physical Science
Architect:
P2S Engineering
Construction Manager:
Bernards
Contractor:
T & D Communications, Inc.
Contract Start:
May 14, 2009
Contract Completion:
November 6, 2009
Original Contract:
$ 154,882
Approved Change Orders:
$ ($5,127)
Revised Contract:
$ 149,755
Scope: The Data and Telecom Cabling project involves the
installation of new data and fiber cabling for the Visual and
Performing Arts Complex, New Gymnasium, and the
Physical Science Building. The work was separated into
three (3) phases: Phase I-New cabling to the Fashion,
Ceramics, and Music buildings in the Performing Arts
Complex and the Physical Science Building; Phase II-New
cabling to the Stadium Press Box and New Gymnasium;
and Phase III-New cabling to the Performing Arts Building
in the Performing Arts Complex.
Completed installation of fiber optic cable in
the Suitomo panel.
Fontana Phase III-Parking Lot
Architect:
HMC Architects
Construction Manager:
Bernards
Contractor:
Bogh Engineering, Inc.
Contract Start:
May 11, 2009
Contract Completion:
October 5, 2009
Original Contract:
$ 1,089,000
Approved Change Orders:
$ 42,618
Revised Contract:
$ 1,131,618
Scope: The Fontana Phase III Parking Lot project consists of the construction of a new parking lot, landscaping, driveway/fire lanes, walkways, utilities, lighting, and signage at the Fontana Campus.
Bio-swale and walkway pavers installed
Chino Health Science Parking Lot
Architect:
MDA Johnson Favaro
Construction Manager:
Chaffey College
Contractor:
Laird Construction Co., Inc.
Contract Start:
June 15, 2009
Contract Completion:
August 15, 2009
Original Contract:
$ 414,550
Approved Change Orders:
$ 0
Revised Contract:
$ 414,550
Scope: The construction of a 100,000 sq. ft. parking lot with 194 parking stalls south and west of the existing parking lots. The parking lot is adjacent to the existing Main Instructional Building located on the Chino Campus.
Chino Campus parking lot, view looking west.
Language Arts/Social Science-HVAC Project
Architect:
P2S Engineering
Construction Manager:
Bernards
Contractor:
Siemens
Contract Start:
May 15, 2009
Contract Completion:
August 14, 2009
Original Contract:
$ 2,700,000
Approved Change Orders:
$ 103,828
Revised Contract:
$ 2,803,828
Scope: Energy project upgrade to the Language Arts and
Social Science buildings, which includes installation of new
air handling equipment and new lighting systems.
Social Science-Completed view of the classroom.
Physical Science Complex-Roof Replacement
Architect:
WWCOT Architect
Construction Manager:
Chaffey College
Contractor:
Cabral Roofing and Waterproofing Corp.
Contract Start:
May 21, 2009
Contract Completion:
July 17, 2009
Original Contract:
$ 623,636
Approved Change Orders:
$ 0
Revised Contract:
$ 623,636
Scope: Replacement of the existing roof at the Physical Science building with a standing seam metal roof.
Completed roof at the Physical Science building.
Library Lawn/Fontana Phase II Landscaping
Architect:
Steve Frenken Landscape Architecture
Construction Manager:
Bernards
Contractor:
Land Forms Landscape Construction
Contract Start:
August 20, 2008
Contract Completion:
November 25, 2008
Original Contract:
$385,000
Approved Change Orders:
($450)
Revised Contract:
$384,550
Scope: This project consists of landscaping and creating the irrigation system for the Fontana Campus Phase II project and the library lawn area at the Rancho Cucamonga campus.
Landscaping at the Fontana Campus.
Landscaping at the Rancho Cucamonga Campus.
Health and Life Science (HLS) Re-Roofing
Architect:
WWCOT Architects
Construction Manager:
Bernards
Contractor:
Best Contracting Services, Inc.
Contract Start:
January 1, 2008
Contract Completion:
June 13, 2008
Original Contract:
$456,169
Approved Change Orders:
$16, 383
Revised Contract:
$472,552
Scope: Comprised of the Health Science Building and the two Life Science buildings, the Health and Life Science Re-Roofing Project, consists of the removal of an existing built up roof on all three locations, and the construction of a new standing seam metal roof.
Newly installed metal roof.
Physical, Health, Life Science (PHLS) Renovations
Architect:
WWCOT Architects
Construction Manager:
Bernards
Contractor:
PW Construction, Inc.
Contract Start:
June 16, 2007
Contract Completion:
Phase 1: June 18, 2008
Phase 2: August 15, 2008
Original Contract:
$8,196,500
Approved Change Orders:
$871,357
Revised Contract:
$9,067,857
Scope: Comprised of 22,997 sq. ft., the Physical, Health, and Life Science Project consists of the renovation of five existing buildings.
Completed dental lab at the Physical Science
Building.
New Marquee Sign
Architect:
Hammel, Green & Abrahamson, Inc.
Construction Manager:
Bernards
Contractor:
Quiel Bros. Electric Sign
Contract Start:
December 27, 2007
Contract Completion:
June 2008
Original Contract:
$180,000
Approved Change Orders:
$1,500
Revised Contract:
$181,500
Scope: Removal and replacement of the existing marquee sign located at the Haven Avenue entrance. The new marquee sign is a double-sided display board constructed of brushed aluminum and baked enamel surfaces.
New marquee sign at Haven Avenue.
Parking Lot #12/Elevator
Architect:
GKK Works
Construction Manager:
Bernards
Contractor:
Edge Development, Inc.
Contract Start:
May 16, 2007
Contract Completion:
November 11, 2007
Original Contract:
1,897,007
Approved Change Orders:
$68,534
Revised Contract:
$1,965,541
Scope: This project completely re-constructs Parking Lot 12 (Phase 1) including two accessible parking areas, sidewalks, lights and landscaping. An elevator (Phase 2) was also constructed connecting the VSS facility to Parking Lot 12.